Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
69
matching recommendationsNAICS | 311 | Food Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UU0235 # 01 Y:2024 | 01 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,664 | $1,013 | Implemented |
UU0236 # 02 Y:2024 | 02 | 2024 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $72,320 | $46,000 | Implemented |
UU0236 # 01 Y:2024 | 01 | 2024 | REPLACE BOILER | $208,300 | $1,070,720 | Implemented |
UU0236 # 04 Y:2024 | 04 | 2024 | INSULATE BARE EQUIPMENT | $5,640 | $3,090 | Implemented |
UU0236 # 03 Y:2024 | 03 | 2024 | INSULATE BARE EQUIPMENT | $16,698 | $11,570 | Implemented |
UU0224 # 02 Y:2023 | 02 | 2023 | VENTILATION SYSTEM TO SHUT OFF WHEN ROOM IS NOT IN USE | $10,206 | $7,560 | Implemented |
UU0224 # 06 Y:2023 | 06 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,460 | $1,382 | Implemented |
UU0224 # 04 Y:2023 | 04 | 2023 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $3,361 | $1,485 | Implemented |
UU0224 # 01 Y:2023 | 01 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $22,006 | $51 | Implemented |
UU0224 # 03 Y:2023 | 03 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $7,006 | $10,650 | Implemented |
BS0120 # 06 Y:2019 | 06 | 2019 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $218 | $105 | Implemented |
BS0074 # 03 Y:2016 | 03 | 2016 | REPLACE BOILER | $2,331 | $14,391 | Implemented |
BS0074 # 09 Y:2016 | 09 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $177 | $483 | Implemented |
BS0074 # 08 Y:2016 | 08 | 2016 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $530 | $7 | Implemented |
BS0074 # 04 Y:2016 | 04 | 2016 | REPAIR OR REPLACE STEAM TRAPS | $2,326 | $5,073 | Implemented |
BS0074 # 02 Y:2016 | 02 | 2016 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $283 | $448 | Implemented |
BS0074 # 01 Y:2016 | 01 | 2016 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $249 | $117 | Implemented |
BS0070 # 03 Y:2016 | 03 | 2016 | PAY UTILITY BILLS ON TIME | $2,153 | $213 | Implemented |
BS0070 # 04 Y:2016 | 04 | 2016 | ESTABLISH EQUIPMENT MAINTENANCE SCHEDULE | $1,079 | $4,500 | Implemented |
BS0070 # 01 Y:2016 | 01 | 2016 | REPAIR OR REPLACE STEAM TRAPS | $13,590 | $12,584 | Implemented |
BS0070 # 07 Y:2016 | 07 | 2016 | REDUCE INFILTRATION TO REFRIGERATED AREAS; ISOLATE HOT EQUIPMENT FROM REFRIGERATED AREAS | $161 | $43 | Implemented |
BS0070 # 06 Y:2016 | 06 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $220 | $585 | Implemented |
BS0070 # 02 Y:2016 | 02 | 2016 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,026 | $744 | Implemented |
BS0070 # 05 Y:2016 | 05 | 2016 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $418 | $14 | Implemented |
BS0039 # 03 Y:2014 | 03 | 2014 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $454 | $241 | Implemented |