IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

543

matching recommendations
Reset
NAICS 311 Food Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
LL0226 # 06 Y:2005 06 2005 INSTALL OCCUPANCY SENSORS $62 $0 Not Implemented
LL0226 # 07 Y:2005 07 2005 BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE $3,875 $350 Implemented
LL0225 # 01 Y:2005 01 2005 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $16,146 $2,000 Implemented
LL0225 # 02 Y:2005 02 2005 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $3,111 $50 Implemented
LL0225 # 03 Y:2005 03 2005 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,676 $400 Implemented
LL0225 # 04 Y:2005 04 2005 INSULATE BARE EQUIPMENT $1,991 $0 Not Implemented
LL0225 # 05 Y:2005 05 2005 INSTALL OCCUPANCY SENSORS $1,445 $0 Not Implemented
LL0225 # 06 Y:2005 06 2005 USE PHOTOCELL CONTROLS $1,100 $0 Not Implemented
LL0225 # 07 Y:2005 07 2005 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $667 $150 Implemented
LL0225 # 08 Y:2005 08 2005 BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE $154,500 $2,500 Implemented
LL0222 # 01 Y:2005 01 2005 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $5,478 $2,000 Implemented
LL0222 # 02 Y:2005 02 2005 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,091 $580 Implemented
LL0222 # 03 Y:2005 03 2005 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $10,261 $500 Implemented
LL0222 # 04 Y:2005 04 2005 INSTALL OCCUPANCY SENSORS $241 $0 Not Implemented
LL0222 # 05 Y:2005 05 2005 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $211 $0 Not Implemented
LL0222 # 06 Y:2005 06 2005 USE RADIANT HEATER FOR SPOT HEATING $123 $0 Not Implemented
LL0222 # 07 Y:2005 07 2005 MINIMIZE WATER USAGE $1,344 $0 Implemented
LL0222 # 08 Y:2005 08 2005 BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE $56,400 $490 Not Implemented
LL0221 # 01 Y:2005 01 2005 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $4,226 $1,500 Implemented
LL0221 # 02 Y:2005 02 2005 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $2,767 $0 Not Implemented
LL0221 # 03 Y:2005 03 2005 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL $726 $0 Not Implemented
LL0221 # 04 Y:2005 04 2005 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $685 $250 Implemented
LL0221 # 05 Y:2005 05 2005 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $645 $0 Not Implemented
LL0221 # 06 Y:2005 06 2005 INSTALL OCCUPANCY SENSORS $26 $0 Not Implemented
LL0221 # 07 Y:2005 07 2005 BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE $31,870 $800 Implemented