IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

1,392

matching recommendations
Reset
NAICS 311 Food Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
SF0572 # 05 Y:2021 05 2021 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $46,961 $45,208 Not Implemented
SF0572 # 06 Y:2021 06 2021 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $1,350 $4,996 Not Implemented
SF0572 # 07 Y:2021 07 2021 REPLACE BOILER $14,321 $72,000 Not Implemented
SF0572 # 08 Y:2021 08 2021 USE SOLAR HEAT TO MAKE ELECTRICTY $343,451 $2,394,442 Not Implemented
SF0572 # 09 Y:2021 09 2021 INSTALL ADEQUATE DRYERS ON AIR LINES TO ELIMINATE BLOWDOWN $134,491 $56,667 Not Implemented
SF0572 # 10 Y:2021 10 2021 INSTALL SUB-METERING EQUIPMENT $8,446 $6,896 Implemented
SD0607 # 01 Y:2021 01 2021 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $26,888 $500 Not Implemented
SD0607 # 02 Y:2021 02 2021 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL $17,809 $38,800 Not Implemented
SD0607 # 03 Y:2021 03 2021 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $13,885 $2,100 Not Implemented
SD0607 # 04 Y:2021 04 2021 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $2,753 $568 Not Implemented
SD0607 # 05 Y:2021 05 2021 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,289 $2,741 Not Implemented
SD0607 # 06 Y:2021 06 2021 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $794 $760 Not Implemented
SD0607 # 07 Y:2021 07 2021 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $481 $706 Not Implemented
SD0607 # 08 Y:2021 08 2021 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $487 $540 Not Implemented
SD0601 # 01 Y:2020 01 2020 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $714 $1,555 Implemented
SD0601 # 02 Y:2020 02 2020 INSTALL OCCUPANCY SENSORS $295 $504 Implemented
SD0601 # 03 Y:2020 03 2020 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $139 $225 Implemented
SD0601 # 04 Y:2020 04 2020 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $130 $360 Not Implemented
SF0558 # 01 Y:2020 01 2020 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $4,941 $0 Implemented
SF0558 # 02 Y:2020 02 2020 USE STEAM PRESSURE REDUCTION TO GENERATE POWER $98,999 $34,416 Implemented
SF0558 # 03 Y:2020 03 2020 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,186 $525 Not Implemented
SF0558 # 04 Y:2020 04 2020 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $9,252 $4,542 Implemented
SF0558 # 05 Y:2020 05 2020 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $4,759 $2,995 Implemented
SF0558 # 06 Y:2020 06 2020 INSULATE BARE EQUIPMENT $282 $379 Implemented
SF0558 # 07 Y:2020 07 2020 USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER $30,342 $50,211 Not Implemented