Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
112
matching recommendationsNAICS | 311 | Food Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SF0423 # 11 Y:2012 | 11 | 2012 | REPLACE ELECTRIC MOTORS WITH BACK PRESSURE STEAM TURBINES AND USE EXHAUST STEAM FOR PROCESS HEAT | $104,307 | $469,980 | Not Implemented |
SF0423 # 06 Y:2012 | 06 | 2012 | INSULATE BARE EQUIPMENT | $4,091 | $4,108 | Implemented |
SF0423 # 02 Y:2012 | 02 | 2012 | REPAIR AND ELIMINATE STEAM LEAKS | $4,512 | $0 | Implemented |
SF0423 # 03 Y:2012 | 03 | 2012 | INSTALL SET-BACK TIMERS | $3,656 | $0 | Implemented |
SF0423 # 04 Y:2012 | 04 | 2012 | REPAIR OR REPLACE STEAM TRAPS | $5,375 | $3,925 | Implemented |
SF0423 # 07 Y:2012 | 07 | 2012 | INSTALL OCCUPANCY SENSORS | $14,919 | $21,094 | Implemented |
SF0423 # 09 Y:2012 | 09 | 2012 | INSULATE BARE EQUIPMENT | $2,993 | $7,655 | Implemented |
SF0423 # 10 Y:2012 | 10 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $42,535 | $127,175 | Implemented |
SF0423 # 08 Y:2012 | 08 | 2012 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $406 | $1,040 | Implemented |
SF0423 # 05 Y:2012 | 05 | 2012 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $7,157 | $5,079 | Not Implemented |
SF0423 # 01 Y:2012 | 01 | 2012 | CLOSE OFF UNNEEDED STEAM LINES | $417 | $0 | Implemented |
SF0423 # 13 Y:2012 | 13 | 2012 | PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST | $26,214 | $85,490 | Not Implemented |
SF0423 # 12 Y:2012 | 12 | 2012 | RECOVER AND REUSE COOLING WATER | $4,700 | $700 | Implemented |
SF0422 # 07 Y:2012 | 07 | 2012 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,287 | $3,924 | Not Implemented |
SF0422 # 04 Y:2012 | 04 | 2012 | USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY | $47,040 | $16,100 | Not Implemented |
SF0422 # 06 Y:2012 | 06 | 2012 | RECOVER WASTE HEAT FROM EQUIPMENT | $9,464 | $10,283 | Not Implemented |
SF0422 # 02 Y:2012 | 02 | 2012 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $642 | $43 | Not Implemented |
SF0422 # 03 Y:2012 | 03 | 2012 | SHUT OFF COOLING IF COLD OUTSIDE AIR WILL COOL PROCESS | $36,414 | $12,500 | Not Implemented |
SF0422 # 10 Y:2012 | 10 | 2012 | ADOPT IN-HOUSE MATERIAL GENERATION | $15,798 | $22,322 | Not Implemented |
SF0422 # 01 Y:2012 | 01 | 2012 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $3,969 | $0 | Not Implemented |
SF0422 # 08 Y:2012 | 08 | 2012 | INSTALL OCCUPANCY SENSORS | $1,288 | $3,390 | Not Implemented |
SF0422 # 05 Y:2012 | 05 | 2012 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $662 | $228 | Not Implemented |
SF0422 # 09 Y:2012 | 09 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,693 | $31,027 | Not Implemented |
SD0458 # 03 Y:2012 | 03 | 2012 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $29,502 | $58,740 | Not Implemented |
SD0458 # 07 Y:2012 | 07 | 2012 | USE MINIMUM STEAM OPERATING PRESSURE | $1,107 | $200 | Not Implemented |