Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
246
matching recommendationsNAICS | 31111 | Animal Food Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SF0317 # 02 Y:2005 | 02 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,124 | $948 | Implemented |
SF0317 # 03 Y:2005 | 03 | 2005 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,170 | $771 | Implemented |
SF0317 # 05 Y:2005 | 05 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $187 | $480 | Implemented |
SF0317 # 07 Y:2005 | 07 | 2005 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $12,370 | $50,000 | Implemented |
SF0317 # 08 Y:2005 | 08 | 2005 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,189 | $5,346 | Implemented |
SU0222 # 01 Y:2005 | 01 | 2005 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $7,489 | $0 | Implemented |
SU0222 # 03 Y:2005 | 03 | 2005 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,352 | $0 | Implemented |
SU0222 # 04 Y:2005 | 04 | 2005 | INSULATE BARE EQUIPMENT | $5,727 | $142 | Implemented |
SU0222 # 05 Y:2005 | 05 | 2005 | INSTALL TURBULATORS | $2,357 | $246 | Implemented |
SU0222 # 06 Y:2005 | 06 | 2005 | INCREASE EFFICIENCY OF TRUCKS | $15,840 | $2,350 | Implemented |
SU0222 # 07 Y:2005 | 07 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,578 | $264 | Implemented |
SU0222 # 08 Y:2005 | 08 | 2005 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $521 | $206 | Implemented |
SU0222 # 10 Y:2005 | 10 | 2005 | INSTALL OCCUPANCY SENSORS | $211 | $127 | Implemented |
SU0222 # 11 Y:2005 | 11 | 2005 | INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS | $1,287 | $895 | Implemented |
SU0222 # 12 Y:2005 | 12 | 2005 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $200 | $342 | Implemented |
SU0222 # 13 Y:2005 | 13 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $155 | $292 | Implemented |
LM0103 # 04 Y:2005 | 04 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $49,470 | $72,000 | Implemented |
CO0567 # 02 Y:2005 | 02 | 2005 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,013 | $1,156 | Implemented |
CO0567 # 03 Y:2005 | 03 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,500 | $11,600 | Implemented |
CO0567 # 04 Y:2005 | 04 | 2005 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $2,350 | $4,820 | Implemented |
CO0567 # 05 Y:2005 | 05 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $510 | $1,810 | Implemented |
UD0720 # 02 Y:2005 | 02 | 2005 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $5,769 | $0 | Implemented |
UD0720 # 03 Y:2005 | 03 | 2005 | OPTIMIZE PLANT POWER FACTOR | $3,870 | $6,000 | Implemented |
UD0720 # 04 Y:2005 | 04 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,757 | $3,200 | Implemented |
UD0720 # 05 Y:2005 | 05 | 2005 | INSTALL / REPAIR INSULATION ON STEAM LINES | $2,200 | $225 | Implemented |