Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
88
matching recommendationsNAICS | 3114 | Fruit and Vegetable Preserving and Specialty Food Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MI0386 # 02 Y:2021 | 02 | 2021 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $19,620 | $43,782 | Implemented |
MI0386 # 04 Y:2021 | 04 | 2021 | USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER | $6,129 | $15,000 | Implemented |
MI0386 # 05 Y:2021 | 05 | 2021 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $1,559 | $1,827 | Implemented |
UF0539 # 04 Y:2019 | 04 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,250 | $11,853 | Implemented |
UF0539 # 02 Y:2019 | 02 | 2019 | INSTALL DESICCANT HUMIDITY CONTROL SYSTEM | $6,161 | $518 | Implemented |
UF0539 # 05 Y:2019 | 05 | 2019 | INSTALL OCCUPANCY SENSORS | $1,002 | $3,662 | Implemented |
UF0539 # 01 Y:2019 | 01 | 2019 | USE SOLAR HEAT TO MAKE ELECTRICTY | $38,262 | $166,880 | Implemented |
UF0521 # 03 Y:2018 | 03 | 2018 | REPAIR AND ELIMINATE STEAM LEAKS | $13,844 | $562 | Implemented |
UF0521 # 10 Y:2018 | 10 | 2018 | MAKE A NEW BY-PRODUCT | $243,164 | $58,810 | Implemented |
UF0521 # 09 Y:2018 | 09 | 2018 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE HANDLING COSTS | $39,645 | $66,000 | Implemented |
UF0521 # 08 Y:2018 | 08 | 2018 | INSTALL OCCUPANCY SENSORS | $1,160 | $1,149 | Implemented |
UF0521 # 07 Y:2018 | 07 | 2018 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,356 | $0 | Implemented |
UF0521 # 01 Y:2018 | 01 | 2018 | INCREASE AMOUNT OF CONDENSATE RETURNED | $45,855 | $11,386 | Implemented |
UF0521 # 06 Y:2018 | 06 | 2018 | IMPROVE COMBUSTION CONTROL CAPABILITY | $3,586 | $2,800 | Implemented |
UF0521 # 05 Y:2018 | 05 | 2018 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $7,972 | $4,143 | Implemented |
UF0521 # 04 Y:2018 | 04 | 2018 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $10,195 | $15,000 | Implemented |
UF0521 # 02 Y:2018 | 02 | 2018 | USE SOLAR HEAT TO MAKE ELECTRICTY | $41,132 | $314,072 | Implemented |
MI0327 # 07 Y:2018 | 07 | 2018 | USE UTILITY CONTROLLED POWER MANAGEMENT | $2,349 | $80 | Implemented |
MI0327 # 04 Y:2018 | 04 | 2018 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $3,743 | $520 | Implemented |
MI0327 # 03 Y:2018 | 03 | 2018 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $5,990 | $7,485 | Implemented |
MI0327 # 02 Y:2018 | 02 | 2018 | TURN OFF EQUIPMENT WHEN NOT IN USE | $12,641 | $3,600 | Implemented |
UF0513 # 02 Y:2017 | 02 | 2017 | ISOLATE HOT OR COLD EQUIPMENT | $25,893 | $3,150 | Implemented |
UF0513 # 03 Y:2017 | 03 | 2017 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $14,487 | $23,157 | Implemented |
UF0513 # 04 Y:2017 | 04 | 2017 | MINIMIZE NON-ESSENTIAL MATERIAL IN HEAT TREATMENT PROCESS | $7,542 | $0 | Implemented |
UF0513 # 05 Y:2017 | 05 | 2017 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $6,342 | $27,695 | Implemented |