Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
102
matching recommendationsNAICS | 3114 | Fruit and Vegetable Preserving and Specialty Food Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MAS032 # 03 Y:2012 | 03 | 2012 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $7,897 | $38,000 | Not Implemented |
MAS032 # 05 Y:2012 | 05 | 2012 | INSULATE BARE EQUIPMENT | $1,008 | $730 | Not Implemented |
MAS032 # 02 Y:2012 | 02 | 2012 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $8,141 | $8,000 | Not Implemented |
MAS032 # 01 Y:2012 | 01 | 2012 | MODERATE COOLING TOWER OUTLET TEMPERATURE | $8,920 | $8,000 | Not Implemented |
MAS032 # 06 Y:2012 | 06 | 2012 | INSULATE BARE EQUIPMENT | $256 | $400 | Implemented |
MAS032 # 04 Y:2012 | 04 | 2012 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $5,230 | $20,000 | Not Implemented |
SF0423 # 09 Y:2012 | 09 | 2012 | INSULATE BARE EQUIPMENT | $2,993 | $7,655 | Implemented |
SF0423 # 13 Y:2012 | 13 | 2012 | PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST | $26,214 | $85,490 | Not Implemented |
SF0423 # 12 Y:2012 | 12 | 2012 | RECOVER AND REUSE COOLING WATER | $4,700 | $700 | Implemented |
SF0423 # 11 Y:2012 | 11 | 2012 | REPLACE ELECTRIC MOTORS WITH BACK PRESSURE STEAM TURBINES AND USE EXHAUST STEAM FOR PROCESS HEAT | $104,307 | $469,980 | Not Implemented |
SF0423 # 10 Y:2012 | 10 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $42,535 | $127,175 | Implemented |
SF0423 # 05 Y:2012 | 05 | 2012 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $7,157 | $5,079 | Not Implemented |
SF0423 # 08 Y:2012 | 08 | 2012 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $406 | $1,040 | Implemented |
SF0423 # 04 Y:2012 | 04 | 2012 | REPAIR OR REPLACE STEAM TRAPS | $5,375 | $3,925 | Implemented |
SF0423 # 01 Y:2012 | 01 | 2012 | CLOSE OFF UNNEEDED STEAM LINES | $417 | $0 | Implemented |
SF0423 # 02 Y:2012 | 02 | 2012 | REPAIR AND ELIMINATE STEAM LEAKS | $4,512 | $0 | Implemented |
SF0423 # 07 Y:2012 | 07 | 2012 | INSTALL OCCUPANCY SENSORS | $14,919 | $21,094 | Implemented |
SF0423 # 03 Y:2012 | 03 | 2012 | INSTALL SET-BACK TIMERS | $3,656 | $0 | Implemented |
SF0423 # 06 Y:2012 | 06 | 2012 | INSULATE BARE EQUIPMENT | $4,091 | $4,108 | Implemented |
AM0620 # 06 Y:2012 | 06 | 2012 | KEEP DOORS AND WINDOWS SHUT WHEN NOT ON USE | $1,965 | $240 | Implemented |
AM0620 # 07 Y:2012 | 07 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,505 | $750 | Not Implemented |
AM0620 # 08 Y:2012 | 08 | 2012 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $1,390 | $0 | Implemented |
AM0620 # 09 Y:2012 | 09 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,270 | $3,290 | Implemented |
AM0620 # 10 Y:2012 | 10 | 2012 | INSULATE BARE EQUIPMENT | $1,030 | $1,650 | Implemented |
AM0620 # 11 Y:2012 | 11 | 2012 | USE SYNTHETIC LUBRICANT | $515 | $0 | Not Implemented |