Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
29
matching recommendationsNAICS | 3115 | Dairy Product Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UF0398 # 07 Y:2007 | 07 | 2007 | USE OPTIMUM THICKNESS INSULATION | $32,078 | $6,105 | Not Implemented |
UF0398 # 06 Y:2007 | 06 | 2007 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $3,060 | $1,600 | Not Implemented |
UF0398 # 05 Y:2007 | 05 | 2007 | REPAIR OR REPLACE STEAM TRAPS | $4,676 | $218 | Not Implemented |
UF0398 # 04 Y:2007 | 04 | 2007 | INSTALL OCCUPANCY SENSORS | $806 | $118 | Not Implemented |
UF0398 # 03 Y:2007 | 03 | 2007 | LOWER LIGHT FIXTURES IN HIGH CEILING AREAS | $477 | $150 | Not Implemented |
UF0398 # 02 Y:2007 | 02 | 2007 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $940 | $0 | Not Implemented |
UF0398 # 01 Y:2007 | 01 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $48,081 | $134,669 | Not Implemented |
UF0398 # 08 Y:2007 | 08 | 2007 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $547 | $0 | Not Implemented |
UF0398 # 09 Y:2007 | 09 | 2007 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $6,769 | $19,429 | Not Implemented |
UF0398 # 10 Y:2007 | 10 | 2007 | OPTIMIZE PLANT POWER FACTOR | $209,563 | $17,000 | Not Implemented |
MA0614 # 02 Y:2007 | 02 | 2007 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $13,036 | $8,400 | Implemented |
MA0614 # 07 Y:2007 | 07 | 2007 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $4,376 | $20,000 | Not Implemented |
MA0614 # 06 Y:2007 | 06 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,749 | $31,477 | Implemented |
MA0614 # 05 Y:2007 | 05 | 2007 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $6,416 | $9,000 | Not Implemented |
MA0614 # 04 Y:2007 | 04 | 2007 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,118 | $1,600 | Implemented |
MA0614 # 03 Y:2007 | 03 | 2007 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $12,870 | $0 | Implemented |
MA0614 # 01 Y:2007 | 01 | 2007 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $16,978 | $5,000 | Implemented |
MI0142 # 05 Y:2007 | 05 | 2007 | TURN OFF EQUIPMENT WHEN NOT IN USE | $22,540 | $850 | Implemented |
MI0142 # 06 Y:2007 | 06 | 2007 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $14,779 | $30 | Not Implemented |
MI0142 # 04 Y:2007 | 04 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $36,407 | $68,250 | Not Implemented |
MI0142 # 03 Y:2007 | 03 | 2007 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $46,802 | $1,074 | Not Implemented |
MI0142 # 02 Y:2007 | 02 | 2007 | TURN OFF EQUIPMENT WHEN NOT IN USE | $70,674 | $34 | Implemented |
MI0142 # 01 Y:2007 | 01 | 2007 | HEAT WATER WITH EXHAUST HEAT | $406,657 | $46,000 | Not Implemented |
SU0247 # 01 Y:2007 | 01 | 2007 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,479 | $0 | Not Implemented |
SU0247 # 02 Y:2007 | 02 | 2007 | REPAIR AND ELIMINATE STEAM LEAKS | $41,200 | $140 | Implemented |