Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
259
matching recommendationsNAICS | 311514 | Dry, Condensed, and Evaporated Dairy Product Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UC2415 # 05 Y:2024 | 05 | 2024 | OPTIMIZE PLANT POWER FACTOR | $32,064 | $27,307 | n/a |
UC2415 # 02 Y:2024 | 02 | 2024 | PAY UTILITY BILLS ON TIME | $5,824 | $0 | n/a |
UC2415 # 01 Y:2024 | 01 | 2024 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $78,972 | $0 | n/a |
UC2415 # 06 Y:2024 | 06 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $11,011 | $75 | n/a |
UC2415 # 04 Y:2024 | 04 | 2024 | USE BATTERY STORAGE FOR DEMAND CONTROL | $81,652 | $611,715 | n/a |
UC2415 # 03 Y:2024 | 03 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $109,123 | $769,066 | n/a |
SF0621 # 06 Y:2024 | 06 | 2024 | INCREASE AMOUNT OF CONDENSATE RETURNED | $335,892 | $109,275 | n/a |
SF0621 # 02 Y:2024 | 02 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,882 | $0 | n/a |
SF0621 # 04 Y:2024 | 04 | 2024 | ELIMINATE LEAKS IN WATER LINES AND VALVES | $7,560 | $700 | n/a |
SF0621 # 03 Y:2024 | 03 | 2024 | REPAIR OR REPLACE STEAM TRAPS | $6,435 | $478 | n/a |
SF0621 # 01 Y:2024 | 01 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $12,755 | $300 | n/a |
SF0621 # 05 Y:2024 | 05 | 2024 | INSTALL STEAM TRAP | $9,822 | $1,988 | n/a |
SF0621 # 11 Y:2024 | 11 | 2024 | USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER | $9,426 | $15,810 | n/a |
SF0621 # 08 Y:2024 | 08 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $6,248 | $2,796 | n/a |
SF0621 # 09 Y:2024 | 09 | 2024 | INSULATE BARE EQUIPMENT | $17,564 | $9,294 | n/a |
SF0621 # 07 Y:2024 | 07 | 2024 | USE FLOW CONTROL VALVES ON EQUIPMENT TO OPTIMIZE WATER USE | $6,048 | $1,839 | n/a |
SF0621 # 10 Y:2024 | 10 | 2024 | INSTALL ISOLATION TRANSFORMER ON ADJUSTABLE FREQUENCY DRIVE | $26,726 | $23,394 | n/a |
SF0621 # 12 Y:2024 | 12 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $238,787 | $1,065,639 | n/a |
SF0606 # 01 Y:2023 | 01 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $15,495 | $1,440 | Implemented |
SF0606 # 04 Y:2023 | 04 | 2023 | INSULATE BARE EQUIPMENT | $5,279 | $5,910 | Implemented |
SF0606 # 05 Y:2023 | 05 | 2023 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $4,502 | $8,173 | Implemented |
SF0606 # 07 Y:2023 | 07 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $112,666 | $923,010 | Not Implemented |
SF0606 # 06 Y:2023 | 06 | 2023 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $7,028 | $31,579 | Not Implemented |
SF0606 # 03 Y:2023 | 03 | 2023 | INSULATE BARE EQUIPMENT | $1,107 | $564 | Implemented |
SF0606 # 02 Y:2023 | 02 | 2023 | USE MINIMUM STEAM OPERATING PRESSURE | $5,475 | $60 | Implemented |