Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
43
matching recommendationsNAICS | 3116 | Animal Slaughtering and Processing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IP0108 # 03 Y:2018 | 03 | 2018 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $12,119 | $600 | Not Implemented |
IP0108 # 04 Y:2018 | 04 | 2018 | INSTALL OCCUPANCY SENSORS | $2,230 | $339 | Not Implemented |
IP0108 # 05 Y:2018 | 05 | 2018 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $1,465 | $322 | Not Implemented |
IP0108 # 06 Y:2018 | 06 | 2018 | USE SOLAR HEAT TO MAKE ELECTRICTY | $6,000 | $3,479 | Not Implemented |
IP0108 # 07 Y:2018 | 07 | 2018 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $115 | $53 | Not Implemented |
IP0108 # 08 Y:2018 | 08 | 2018 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $685 | $1,022 | Not Implemented |
IP0108 # 09 Y:2018 | 09 | 2018 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,070 | $2,129 | Not Implemented |
IP0108 # 10 Y:2018 | 10 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,909 | $19,975 | Not Implemented |
IP0108 # 12 Y:2018 | 12 | 2018 | OPTIMIZE PLANT POWER FACTOR | $864 | $4,146 | Not Implemented |
IC0115 # 01 Y:2006 | 01 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,445 | $26,134 | Implemented |
IC0115 # 02 Y:2006 | 02 | 2006 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $3,985 | $16,831 | Implemented |
IC0115 # 03 Y:2006 | 03 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $11,680 | $65,036 | Implemented |
IC0115 # 04 Y:2006 | 04 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $272 | $420 | Implemented |
IC0115 # 05 Y:2006 | 05 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $159 | $380 | Not Implemented |
IC0115 # 06 Y:2006 | 06 | 2006 | INSTALL DIRECT ACTING UNITS IN PLACE OF COMPRESSED AIR PRESSURE SYSTEM IN SAFETY SYSTEM | $54 | $284 | Implemented |
IC0115 # 07 Y:2006 | 07 | 2006 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $142,200 | $195,625 | Not Implemented |
IC0115 # 08 Y:2006 | 08 | 2006 | REPLACE BOILER | $125,042 | $193,200 | Implemented |
IC0115 # 09 Y:2006 | 09 | 2006 | REDUCE EXCESS STEAM BLEEDING | $29,262 | $5,000 | Implemented |