IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

49

matching recommendations
Reset
NAICS 3116 Animal Slaughtering and Processing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OK1082 # 06 Y:2023 06 2023 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $46,475 $36,319 Implemented
OK1082 # 03 Y:2023 03 2023 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $12,649 $2,715 Implemented
OK1082 # 05 Y:2023 05 2023 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,243 $0 Not Implemented
OK1082 # 01 Y:2023 01 2023 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $11,804 $14,599 Implemented
OK1082 # 02 Y:2023 02 2023 USE SOLAR HEAT TO MAKE ELECTRICTY $22,696 $230,880 Not Implemented
OK1082 # 04 Y:2023 04 2023 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $3,847 $323 Implemented
OK1020 # 07 Y:2019 07 2019 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $4,410 $1,270 Not Implemented
OK1020 # 06 Y:2019 06 2019 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $19,990 $0 Not Implemented
OK1020 # 04 Y:2019 04 2019 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $84,978 $73,560 Not Implemented
OK1020 # 05 Y:2019 05 2019 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $33,536 $500 Not Implemented
OK1020 # 03 Y:2019 03 2019 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $111,877 $100,000 Not Implemented
OK1020 # 02 Y:2019 02 2019 OPTIMIZE PLANT POWER FACTOR $91,270 $50,570 Not Implemented
OK1020 # 01 Y:2019 01 2019 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $164,531 $0 Not Implemented
OK0951 # 02 Y:2016 02 2016 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $4,244 $12,740 Not Implemented
OK0951 # 11 Y:2016 11 2016 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $2,880 $0 Not Implemented
OK0951 # 10 Y:2016 10 2016 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $13,152 $0 Not Implemented
OK0951 # 09 Y:2016 09 2016 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $159,843 $40,000 Not Implemented
OK0951 # 08 Y:2016 08 2016 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $14,014 $4,000 Not Implemented
OK0951 # 07 Y:2016 07 2016 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $17,684 $1,972 Not Implemented
OK0951 # 06 Y:2016 06 2016 INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT $1,980 $7,000 Not Implemented
OK0951 # 05 Y:2016 05 2016 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS $5,675 $2,816 Implemented
OK0951 # 04 Y:2016 04 2016 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $8,904 $3,000 Implemented
OK0951 # 03 Y:2016 03 2016 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $26,114 $42,500 Not Implemented
OK0951 # 01 Y:2016 01 2016 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $48,548 $62,561 Not Implemented
OK0933 # 12 Y:2016 12 2016 SELL COMBUSTIBLE WASTE $24,120 $480 Not Implemented