Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
675
matching recommendationsNAICS | 3118 | Bakeries and Tortilla Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UL2203 # 01 Y:2022 | 01 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $37,530 | $37,026 | Implemented |
UL2203 # 03 Y:2022 | 03 | 2022 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $6,985 | $0 | Implemented |
UL2203 # 05 Y:2022 | 05 | 2022 | OPTIMIZE PLANT POWER FACTOR | $79,271 | $45,460 | Implemented |
LS2212 # 05 Y:2022 | 05 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $389 | $468 | Implemented |
LS2212 # 03 Y:2022 | 03 | 2022 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $545 | $150 | Implemented |
LS2212 # 02 Y:2022 | 02 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,007 | $360 | Implemented |
LS2212 # 01 Y:2022 | 01 | 2022 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $572 | $0 | Implemented |
UF0574 # 03 Y:2022 | 03 | 2022 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $22,318 | $12,420 | Implemented |
UF0574 # 02 Y:2022 | 02 | 2022 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $38,315 | $45,847 | Implemented |
UF0574 # 01 Y:2022 | 01 | 2022 | USE SOLAR HEAT TO MAKE ELECTRICTY | $57,729 | $322,608 | Implemented |
UF0574 # 04 Y:2022 | 04 | 2022 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $13,484 | $20,340 | Implemented |
UF0574 # 05 Y:2022 | 05 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,896 | $25,258 | Implemented |
UF0574 # 06 Y:2022 | 06 | 2022 | MAINTAIN AIR FILTERS BY CLEANING OR REPLACEMENT | $5,512 | $600 | Implemented |
UF0574 # 07 Y:2022 | 07 | 2022 | OPTIMIZE PLANT POWER FACTOR | $5,422 | $24,763 | Implemented |
UF0574 # 11 Y:2022 | 11 | 2022 | LEVEL ONE – ADD COMMUNICATION USING IIOT DEVICES TO EXISTING CONTROL SYSTEM TO MODIFY OPERATIONS | $287,926 | $0 | Implemented |
UF0574 # 12 Y:2022 | 12 | 2022 | LEVEL ZERO – INSTALL CONTROL SYSTEMS FOR EXISTING EQUIPMENT | $22,157 | $0 | Implemented |
UF0574 # 13 Y:2022 | 13 | 2022 | ADD/MODIFY EQUIPMENT TO IMPROVE DRYING PROCESS | $16,503 | $80,000 | Implemented |
UF0574 # 14 Y:2022 | 14 | 2022 | MINIMIZE CONTAMINATION OF WATER BEFORE TREATMENT | $18,108 | $45,538 | Implemented |
UF0574 # 15 Y:2022 | 15 | 2022 | ELIMINATE LEAKS IN WATER LINES AND VALVES | $1,082 | $88 | Implemented |
IC0247 # 01 Y:2021 | 01 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,735 | $1,539 | Implemented |
IC0247 # 02 Y:2021 | 02 | 2021 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $2,646 | $64,258 | Implemented |
IC0247 # 04 Y:2021 | 04 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,040 | $5,000 | Implemented |
AS0490 # 02 Y:2020 | 02 | 2020 | UPGRADE CONTROLS ON COMPRESSORS | $3,534 | $3,368 | Implemented |
AS0490 # 03 Y:2020 | 03 | 2020 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $2,729 | $410 | Implemented |
AS0490 # 04 Y:2020 | 04 | 2020 | KEEP EQUIPMENT CLEAN | $991 | $464 | Implemented |