Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
90
matching recommendationsNAICS | 31181 | Bread and Bakery Product Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
CM1019 # 01 Y:2023 | 01 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $44,370 | $657,982 | n/a |
CM1019 # 02 Y:2023 | 02 | 2023 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $93,012 | $807,500 | n/a |
CM1019 # 03 Y:2023 | 03 | 2023 | INCREASE EFFICIENCY OF TRUCKS | $43,375 | $394,000 | n/a |
CM1019 # 04 Y:2023 | 04 | 2023 | INSTALL SENSORS TO DETECT AND AVOID JAMS | $7,058 | $30,570 | n/a |
IP0172 # 05 Y:2023 | 05 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $7,584 | $8,088 | Not Implemented |
IP0172 # 04 Y:2023 | 04 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $14,315 | $14,588 | Not Implemented |
IP0172 # 03 Y:2023 | 03 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,870 | $1,313 | Not Implemented |
IP0172 # 02 Y:2023 | 02 | 2023 | INSTALL OR UPGRADE INSULATION ON HVAC DISTRIBUTION SYSTEMS | $512 | $83 | Not Implemented |
IP0172 # 01 Y:2023 | 01 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,640 | $132 | Not Implemented |
NT0003 # 01 Y:2023 | 01 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,267 | $5,705 | Not Implemented |
GT0965 # 05 Y:2023 | 05 | 2023 | USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT | $103,640 | $350,000 | Not Implemented |
GT0965 # 04 Y:2023 | 04 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $281 | $927 | Implemented |
GT0965 # 03 Y:2023 | 03 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $13,164 | $800 | Implemented |
GT0965 # 02 Y:2023 | 02 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $34,014 | $1,850 | Implemented |
GT0965 # 01 Y:2023 | 01 | 2023 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $23,363 | $800 | Not Implemented |
NT0003 # 04 Y:2023 | 04 | 2023 | INSTALL OCCUPANCY SENSORS | $3,289 | $1,600 | Not Implemented |
NT0003 # 02 Y:2023 | 02 | 2023 | OPTIMIZE PLANT POWER FACTOR | $12,262 | $21,725 | Not Implemented |
NT0003 # 05 Y:2023 | 05 | 2023 | REPLACE AIR CURTAIN DOORS WITH SOLID DOORS | $2,238 | $3,193 | Not Implemented |
NT0003 # 06 Y:2023 | 06 | 2023 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $23,020 | $185,220 | Not Implemented |
NT0003 # 03 Y:2023 | 03 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,623 | $24,707 | Not Implemented |
TT0290 # 02 Y:2023 | 02 | 2023 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $21,000 | $2,000 | Not Implemented |
TT0290 # 05 Y:2023 | 05 | 2023 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $911 | $30 | Implemented |
TT0290 # 04 Y:2023 | 04 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,702 | $1,755 | Implemented |
TT0290 # 03 Y:2023 | 03 | 2023 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,477 | $10,500 | Not Implemented |
TT0290 # 01 Y:2023 | 01 | 2023 | UPGRADE OBSOLETE EQUIPMENT | $106,623 | $200,000 | Implemented |