Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,036
matching recommendationsNAICS | 311812 | Commercial Bakeries |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AS0521 # 01 Y:2022 | 01 | 2022 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $52,178 | $1,517 | Implemented |
AS0521 # 02 Y:2022 | 02 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $28,344 | $6,500 | Implemented |
AS0521 # 03 Y:2022 | 03 | 2022 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $755 | $5,520 | Not Implemented |
AS0521 # 04 Y:2022 | 04 | 2022 | INSTALL OCCUPANCY SENSORS | $835 | $814 | Implemented |
AS0521 # 05 Y:2022 | 05 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $191 | $514 | Implemented |
AS0521 # 06 Y:2022 | 06 | 2022 | USE OPTIMUM THICKNESS INSULATION | $13 | $109 | Implemented |
LS2215 # 01 Y:2022 | 01 | 2022 | LEVEL ZERO – INSTALL CONTROL SYSTEMS FOR EXISTING EQUIPMENT | $50,000 | $0 | Implemented |
LS2215 # 02 Y:2022 | 02 | 2022 | PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST | $9,603 | $1,118 | Implemented |
LS2215 # 03 Y:2022 | 03 | 2022 | INSTALL SENSORS TO DETECT AND AVOID JAMS | $72,450 | $2,400 | Implemented |
LS2215 # 04 Y:2022 | 04 | 2022 | INSTALL TIMERS AND/OR THERMOSTATS | $631 | $75 | Implemented |
LS2215 # 05 Y:2022 | 05 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,461 | $270 | Implemented |
LS2215 # 06 Y:2022 | 06 | 2022 | INSTALL OCCUPANCY SENSORS | $247 | $100 | Implemented |
LS2215 # 07 Y:2022 | 07 | 2022 | LEVEL ONE – ADD COMMUNICATION USING IIOT DEVICES TO EXISTING CONTROL SYSTEM TO MODIFY OPERATIONS | $49,680 | $58,020 | Implemented |
LS2215 # 08 Y:2022 | 08 | 2022 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $6,502 | $14,000 | Not Implemented |
LS2215 # 09 Y:2022 | 09 | 2022 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $188 | $415 | Not Implemented |
KS2201 # 01 Y:2022 | 01 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $11,955 | $5,480 | Implemented |
KS2201 # 02 Y:2022 | 02 | 2022 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,137 | $60 | Implemented |
KS2201 # 03 Y:2022 | 03 | 2022 | LEVEL ZERO – INSTALL CONTROL SYSTEMS FOR EXISTING EQUIPMENT | $1,085 | $4,460 | Not Implemented |
KS2201 # 04 Y:2022 | 04 | 2022 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $39,082 | $154,800 | Implemented |
KS2201 # 05 Y:2022 | 05 | 2022 | USE WASTE HEAT FROM FLUE GASES TO HEAT SPACE CONDITIONING AIR | $7,820 | $2,174 | Not Implemented |
KS2201 # 06 Y:2022 | 06 | 2022 | INSULATE BARE EQUIPMENT | $868 | $1,047 | Not Implemented |
KS2201 # 07 Y:2022 | 07 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $15,572 | $61,880 | Implemented |
KS2201 # 08 Y:2022 | 08 | 2022 | USE SOLAR HEAT TO MAKE ELECTRICTY | $60,974 | $540,200 | Not Implemented |
KS2201 # 09 Y:2022 | 09 | 2022 | CHECK FOR ACCURACY OF UTILITY / POWER METERS | $13,164 | $120 | Implemented |
UL2203 # 01 Y:2022 | 01 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $37,530 | $37,026 | Implemented |