IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

1,762

matching recommendations
Reset
NAICS 3119 Other Food Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
SF0556 # 06 Y:2020 06 2020 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $5,238 $5,536 Implemented
SF0556 # 07 Y:2020 07 2020 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $2,455 $3,366 Implemented
SF0556 # 08 Y:2020 08 2020 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $6,676 $16,092 Implemented
SF0556 # 09 Y:2020 09 2020 USE SOLAR HEAT TO MAKE ELECTRICTY $57,865 $348,493 Implemented
SF0556 # 10 Y:2020 10 2020 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $2,250 $1,064 Not Implemented
SF0555 # 01 Y:2020 01 2020 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $5,084 $0 Implemented
SF0555 # 02 Y:2020 02 2020 INSULATE BARE EQUIPMENT $1,257 $1,080 Implemented
SF0555 # 03 Y:2020 03 2020 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS $3,734 $3,930 Implemented
SF0555 # 04 Y:2020 04 2020 REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT $450,171 $750,000 Not Implemented
SF0555 # 05 Y:2020 05 2020 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $26,221 $33,106 Implemented
SF0555 # 06 Y:2020 06 2020 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $7,764 $20,616 Implemented
SF0555 # 07 Y:2020 07 2020 REPLACE BOILER $14,667 $114,810 Implemented
SF0555 # 08 Y:2020 08 2020 USE SOLAR HEAT TO MAKE ELECTRICTY $63,107 $268,469 Not Implemented
SF0553 # 01 Y:2020 01 2020 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,333 $0 Implemented
SF0553 # 02 Y:2020 02 2020 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,905 $120 Implemented
SF0553 # 03 Y:2020 03 2020 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $289 $41 Implemented
SF0553 # 04 Y:2020 04 2020 AIR CONDITION ONLY SPACE NECESSARY $2,096 $2,344 Implemented
SF0553 # 05 Y:2020 05 2020 INSTALL OCCUPANCY SENSORS $12,409 $22,495 Implemented
SF0553 # 06 Y:2020 06 2020 USE SOLAR HEAT TO MAKE ELECTRICTY $100,613 $451,750 Implemented
SF0552 # 01 Y:2020 01 2020 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $25,284 $0 Not Implemented
SF0552 # 02 Y:2020 02 2020 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,516 $0 Implemented
SF0552 # 03 Y:2020 03 2020 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $575 $137 Implemented
SF0552 # 04 Y:2020 04 2020 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $896 $400 Implemented
SF0552 # 05 Y:2020 05 2020 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $2,065 $1,862 Implemented
SF0552 # 06 Y:2020 06 2020 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $10,077 $12,392 Not Implemented