Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
31
matching recommendationsNAICS | 311930 | Flavoring Syrup and Concentrate Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LE0386 # 10 Y:2014 | 10 | 2014 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $2,010 | $6,000 | Not Implemented |
LE0386 # 09 Y:2014 | 09 | 2014 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $757 | $2,250 | Implemented |
LE0386 # 08 Y:2014 | 08 | 2014 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $6,813 | $20,000 | Not Implemented |
LE0386 # 07 Y:2014 | 07 | 2014 | REPLACE BOILER | $102,338 | $161,800 | Not Implemented |
LE0386 # 06 Y:2014 | 06 | 2014 | PREHEAT COMBUSTION AIR WITH WASTE HEAT | $12,502 | $16,700 | Implemented |
LE0386 # 05 Y:2014 | 05 | 2014 | REPAIR FURNACES AND OVEN DOORS SO THAT THEY SEAL EFFICIENTLY | $451 | $232 | Not Implemented |
LE0386 # 04 Y:2014 | 04 | 2014 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $43,975 | $10,000 | Implemented |
LE0386 # 01 Y:2014 | 01 | 2014 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $8,661 | $32 | Implemented |
LE0386 # 02 Y:2014 | 02 | 2014 | REPAIR AND ELIMINATE STEAM LEAKS | $61,300 | $2,592 | Implemented |
LE0386 # 03 Y:2014 | 03 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $10,910 | $1,000 | Implemented |
WV0377 # 03 Y:2008 | 03 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,568 | $25,978 | Implemented |
WV0377 # 12 Y:2008 | 12 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,192 | $1,202 | Implemented |
WV0377 # 04 Y:2008 | 04 | 2008 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $9,122 | $231 | Implemented |
WV0377 # 05 Y:2008 | 05 | 2008 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $6,506 | $1,000 | Implemented |
WV0377 # 06 Y:2008 | 06 | 2008 | DEVELOP A REPAIR/REPLACE POLICY | $5,730 | $815 | Implemented |
WV0377 # 07 Y:2008 | 07 | 2008 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $4,754 | $3,084 | Not Implemented |
WV0377 # 08 Y:2008 | 08 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,670 | $0 | Implemented |
WV0377 # 09 Y:2008 | 09 | 2008 | UPGRADE CONTROLS ON COMPRESSORS | $2,273 | $1,830 | Not Implemented |
WV0377 # 10 Y:2008 | 10 | 2008 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $1,858 | $7,053 | Not Implemented |
WV0377 # 11 Y:2008 | 11 | 2008 | INSULATE BARE EQUIPMENT | $1,335 | $710 | Implemented |
WV0377 # 02 Y:2008 | 02 | 2008 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $14,777 | $18,980 | Not Implemented |
WV0377 # 01 Y:2008 | 01 | 2008 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $21,957 | $5,000 | Implemented |
LE0246 # 09 Y:2006 | 09 | 2006 | INSTALL OCCUPANCY SENSORS | $1,586 | $450 | Implemented |
LE0246 # 08 Y:2006 | 08 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,948 | $180,000 | Implemented |
LE0246 # 07 Y:2006 | 07 | 2006 | USE UTILITY CONTROLLED POWER MANAGEMENT | $3,000 | $100 | Not Implemented |