Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
712
matching recommendationsNAICS | 31199 | All Other Food Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TT0114 # 02 Y:2013 | 02 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $42 | $0 | Implemented |
TT0114 # 03 Y:2013 | 03 | 2013 | TURN OFF EQUIPMENT WHEN NOT IN USE | $13,529 | $125 | Implemented |
TT0114 # 04 Y:2013 | 04 | 2013 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $6,310 | $9,125 | Not Implemented |
TT0114 # 05 Y:2013 | 05 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $360 | $315 | Implemented |
TT0114 # 06 Y:2013 | 06 | 2013 | INSTALL OCCUPANCY SENSORS | $6,033 | $5,950 | Implemented |
TT0114 # 07 Y:2013 | 07 | 2013 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $7,988 | $15,000 | Not Implemented |
BS0010 # 01 Y:2012 | 01 | 2012 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $289 | $630 | Not Implemented |
BS0010 # 02 Y:2012 | 02 | 2012 | INSULATE BARE EQUIPMENT | $222 | $512 | Implemented |
BS0010 # 03 Y:2012 | 03 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $6,826 | $750 | Not Implemented |
BS0010 # 04 Y:2012 | 04 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $645 | $251 | Implemented |
BS0010 # 05 Y:2012 | 05 | 2012 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $70 | $60 | Not Implemented |
LE0348 # 01 Y:2012 | 01 | 2012 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $31,702 | $24,000 | Implemented |
LE0348 # 02 Y:2012 | 02 | 2012 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,828 | $5,000 | Not Implemented |
LE0348 # 03 Y:2012 | 03 | 2012 | PREHEAT COMBUSTION AIR WITH WASTE HEAT | $12,235 | $43,550 | Not Implemented |
LE0348 # 04 Y:2012 | 04 | 2012 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,951 | $1,940 | Not Implemented |
LE0348 # 05 Y:2012 | 05 | 2012 | REPAIR AND ELIMINATE STEAM LEAKS | $2,368 | $2,300 | Implemented |
LE0348 # 06 Y:2012 | 06 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,650 | $1,600 | Implemented |
LE0348 # 07 Y:2012 | 07 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,956 | $5,700 | Implemented |
LE0348 # 08 Y:2012 | 08 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $120 | $40 | Not Implemented |
BS0008 # 01 Y:2012 | 01 | 2012 | MODIFY FACILITY TO AVOID EXCESS MAINTENANCE COSTS | $9,360 | $350 | Not Implemented |
BS0008 # 02 Y:2012 | 02 | 2012 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,298 | $14,400 | Not Implemented |
BS0008 # 03 Y:2012 | 03 | 2012 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $1,079 | $117 | Not Implemented |
BS0008 # 04 Y:2012 | 04 | 2012 | USE PHOTOCELL CONTROLS | $427 | $227 | Not Implemented |
BS0008 # 05 Y:2012 | 05 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $475 | $15 | Not Implemented |
TT0094 # 01 Y:2012 | 01 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $9,034 | $0 | Not Implemented |