Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

25

matching recommendations
Reset
NAICS 31199 All Other Food Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UW2207 # 04 Y:2022 04 2022 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,631 $2,080 Implemented
UW2207 # 03 Y:2022 03 2022 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $5,582 $12,124 Not Implemented
UW2207 # 02 Y:2022 02 2022 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $685 $112 Implemented
UW2207 # 01 Y:2022 01 2022 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,161 $0 Implemented
BS0131 # 02 Y:2019 02 2019 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $79 $38 Not Implemented
BS0131 # 06 Y:2019 06 2019 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,392 $1,030 Not Implemented
BS0131 # 01 Y:2019 01 2019 INSTALL OCCUPANCY SENSORS $442 $300 Not Implemented
BS0131 # 03 Y:2019 03 2019 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $472 $295 Not Implemented
BS0131 # 04 Y:2019 04 2019 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $204 $412 Not Implemented
BS0131 # 05 Y:2019 05 2019 INSTALL TIMERS AND/OR THERMOSTATS $217 $170 Not Implemented
OR0655 # 01 Y:2015 01 2015 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE $26,151 $0 Not Implemented
OR0655 # 09 Y:2015 09 2015 USE SOLAR HEAT TO MAKE ELECTRICTY $2,480 $20,979 Not Implemented
OR0655 # 08 Y:2015 08 2015 RECOVER WASTE HEAT FROM EQUIPMENT $4,958 $7,816 Not Implemented
OR0655 # 07 Y:2015 07 2015 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE $51,916 $126,000 Not Implemented
OR0655 # 06 Y:2015 06 2015 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $180,695 $251,760 Not Implemented
OR0655 # 05 Y:2015 05 2015 FLASH CONDENSATE TO PRODUCE LOWER PRESSURE STEAM $15,571 $19,050 Not Implemented
OR0655 # 04 Y:2015 04 2015 ADJUST / MAINTAIN FORK LIFT TRUCKS FOR MOST EFFICIENT OPERATION $175,008 $188,400 Not Implemented
OR0655 # 03 Y:2015 03 2015 TURN OFF EQUIPMENT WHEN NOT IN USE $20,211 $1,000 Not Implemented
OR0655 # 02 Y:2015 02 2015 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $4,161 $1,000 Implemented
BS0020 # 01 Y:2013 01 2013 REDESIGN PROCESS $15,024 $15,359 Not Implemented
BS0020 # 02 Y:2013 02 2013 OPTIMIZE PLANT POWER FACTOR $18,318 $19,262 Implemented
BS0020 # 03 Y:2013 03 2013 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $8,893 $71,307 Implemented
BS0020 # 04 Y:2013 04 2013 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $13,831 $15,600 Implemented
BS0020 # 05 Y:2013 05 2013 INSULATE BARE EQUIPMENT $9,887 $5,300 Implemented
BS0020 # 06 Y:2013 06 2013 COVER OPEN TANKS $3,845 $6,050 Not Implemented