Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
16
matching recommendationsNAICS | 311991 | Perishable Prepared Food Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
CI0022 # 01 Y:2023 | 01 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $30,795 | $185,422 | n/a |
CI0022 # 02 Y:2023 | 02 | 2023 | REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | $18,385 | $60,000 | n/a |
CI0022 # 03 Y:2023 | 03 | 2023 | PREHEAT COMBUSTION AIR WITH WASTE HEAT | $17,839 | $9,000 | n/a |
CI0022 # 04 Y:2023 | 04 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $12,948 | $300 | n/a |
CI0022 # 05 Y:2023 | 05 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $10,784 | $0 | n/a |
CI0022 # 06 Y:2023 | 06 | 2023 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $5,312 | $50 | n/a |
CI0022 # 07 Y:2023 | 07 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,547 | $7,400 | n/a |
CI0022 # 08 Y:2023 | 08 | 2023 | INSTALL OCCUPANCY SENSORS | $1,670 | $1,125 | n/a |
CI0017 # 01 Y:2023 | 01 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $271,104 | $1,391,144 | n/a |
CI0017 # 02 Y:2023 | 02 | 2023 | REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | $63,711 | $90,000 | n/a |
CI0017 # 03 Y:2023 | 03 | 2023 | REPLACE BOILER | $25,947 | $36,000 | n/a |
CI0017 # 04 Y:2023 | 04 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $21,971 | $39,000 | n/a |
CI0017 # 05 Y:2023 | 05 | 2023 | USE POWER DURING OFF-PEAK PERIODS | $12,483 | $22,000 | n/a |
CI0017 # 06 Y:2023 | 06 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $11,433 | $1,500 | n/a |
CI0017 # 07 Y:2023 | 07 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $6,491 | $0 | n/a |
CI0017 # 08 Y:2023 | 08 | 2023 | PREHEAT COMBUSTION AIR WITH WASTE HEAT | $1,591 | $5,000 | n/a |