Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
868
matching recommendationsNAICS | 3121 | Beverage Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AS0529 # 06 Y:2022 | 06 | 2022 | Install Anaerobic Digester | $232,359 | $1,128,000 | Implemented |
OK1072 # 01 Y:2022 | 01 | 2022 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $3,650 | $0 | Implemented |
AM0847 # 01 Y:2022 | 01 | 2022 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $55,740 | $5,500 | Implemented |
AM0847 # 02 Y:2022 | 02 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,340 | $1,000 | Implemented |
AM0847 # 03 Y:2022 | 03 | 2022 | OPTIMIZE PLANT POWER FACTOR | $1,420 | $2,240 | Implemented |
AM0847 # 04 Y:2022 | 04 | 2022 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $840 | $10 | Implemented |
AM0847 # 06 Y:2022 | 06 | 2022 | USE SYNTHETIC LUBRICANT | $506 | $220 | Implemented |
AM0847 # 07 Y:2022 | 07 | 2022 | INSTALL OCCUPANCY SENSORS | $355 | $232 | Implemented |
AM0847 # 08 Y:2022 | 08 | 2022 | USE PHOTOCELL CONTROLS | $330 | $110 | Implemented |
AM0847 # 09 Y:2022 | 09 | 2022 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $255 | $50 | Implemented |
LE0520 # 03 Y:2022 | 03 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,247 | $4,450 | Implemented |
GT0958 # 01 Y:2021 | 01 | 2021 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $93,972 | $800 | Implemented |
GT0958 # 02 Y:2021 | 02 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $16,743 | $1,850 | Implemented |
SF0580 # 07 Y:2021 | 07 | 2021 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $19,936 | $49,917 | Implemented |
SF0580 # 06 Y:2021 | 06 | 2021 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $228 | $574 | Implemented |
SF0580 # 05 Y:2021 | 05 | 2021 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $1,242 | $2,702 | Implemented |
SF0580 # 04 Y:2021 | 04 | 2021 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $13,463 | $18,200 | Implemented |
SF0580 # 01 Y:2021 | 01 | 2021 | USE HIGHEST TEMPERATURE FOR CHILLING OR COLD STORAGE | $18,446 | $0 | Implemented |
OR0745 # 01 Y:2021 | 01 | 2021 | REMOVE OR CLOSE OFF UNNEEDED COMPRESSED AIR LINES | $11,633 | $395 | Implemented |
OR0745 # 02 Y:2021 | 02 | 2021 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,360 | $542 | Implemented |
OR0745 # 03 Y:2021 | 03 | 2021 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,286 | $485 | Implemented |
SD0615 # 03 Y:2021 | 03 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $385 | $1,182 | Implemented |
SD0615 # 02 Y:2021 | 02 | 2021 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $540 | $0 | Implemented |
SD0615 # 01 Y:2021 | 01 | 2021 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $4,310 | $6,942 | Implemented |
LS2116 # 02 Y:2021 | 02 | 2021 | INSTALL OCCUPANCY SENSORS | $4,408 | $250 | Implemented |