IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

868

matching recommendations
Reset
NAICS 3121 Beverage Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
SF0569 # 01 Y:2021 01 2021 CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE $5,931 $0 Implemented
SF0569 # 02 Y:2021 02 2021 INSTALL TIMERS AND/OR THERMOSTATS $4,698 $3,740 Implemented
SF0569 # 03 Y:2021 03 2021 SHUT OFF COOLING IF COLD OUTSIDE AIR WILL COOL PROCESS $5,693 $9,138 Implemented
SF0569 # 04 Y:2021 04 2021 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE $7,674 $23,650 Implemented
SF0569 # 05 Y:2021 05 2021 INSTALL OCCUPANCY SENSORS $2,279 $6,956 Implemented
SF0569 # 06 Y:2021 06 2021 USE SOLAR HEAT TO MAKE ELECTRICTY $107,546 $722,227 Implemented
SF0569 # 07 Y:2021 07 2021 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS $143,550 $77,720 Implemented
OK1044 # 03 Y:2021 03 2021 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $14,702 $14,800 Implemented
AM0820 # 01 Y:2021 01 2021 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES $41,395 $5,000 Implemented
AM0820 # 02 Y:2021 02 2021 INSTALL OCCUPANCY SENSORS $8,810 $800 Implemented
AM0820 # 03 Y:2021 03 2021 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $6,591 $6,760 Implemented
AM0820 # 04 Y:2021 04 2021 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,210 $1,000 Implemented
AM0820 # 05 Y:2021 05 2021 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED $1,775 $0 Implemented
AM0820 # 06 Y:2021 06 2021 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $1,360 $1,038 Implemented
DL0189 # 01 Y:2021 01 2021 ELIMINATE LEAKS IN WATER LINES AND VALVES $5,300 $425 Implemented
DL0189 # 04 Y:2021 04 2021 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $28,940 $20,000 Implemented
DL0189 # 05 Y:2021 05 2021 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $13,110 $72,258 Implemented
DL0189 # 06 Y:2021 06 2021 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $12,820 $24,000 Implemented
LS2009 # 02 Y:2020 02 2020 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,136 $360 Implemented
LS2009 # 04 Y:2020 04 2020 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED $71 $50 Implemented
LS2009 # 05 Y:2020 05 2020 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $69 $88 Implemented
LS2009 # 06 Y:2020 06 2020 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,426 $2,260 Implemented
LS2009 # 07 Y:2020 07 2020 INSTALL AUTOMATIC PACKING EQUIPMENT $57,969 $120,000 Implemented
DL0188 # 01 Y:2021 01 2021 ELIMINATE LEAKS IN WATER LINES AND VALVES $900 $0 Implemented
DL0188 # 03 Y:2021 03 2021 REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER $23,050 $9,490 Implemented