Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
32
matching recommendationsNAICS | 31212 | Breweries |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0795 # 01 Y:2024 | 01 | 2024 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $386,550 | $1,582,496 | n/a |
OR0795 # 03 Y:2024 | 03 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $26,223 | $1,293 | n/a |
OR0795 # 04 Y:2024 | 04 | 2024 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $4,228 | $13,714 | n/a |
OR0795 # 02 Y:2024 | 02 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $45,995 | $522,500 | n/a |
OR0770 # 02 Y:2023 | 02 | 2023 | REDUCE SCRAP PRODUCTION | $111,700 | $282,420 | Not Implemented |
OR0770 # 04 Y:2023 | 04 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $206 | $0 | Not Implemented |
OR0770 # 01 Y:2023 | 01 | 2023 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $2,142 | $6,704 | Implemented |
OR0770 # 03 Y:2023 | 03 | 2023 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $4,249 | $9,000 | Implemented |
OR0725 # 04 Y:2019 | 04 | 2019 | REPLACE BOILER | $2,159 | $0 | Not Implemented |
OR0725 # 03 Y:2019 | 03 | 2019 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $126,211 | $375,000 | Implemented |
OR0725 # 02 Y:2019 | 02 | 2019 | RECOVER AND REUSE WASTE MATERIAL | $58,445 | $110,790 | Implemented |
OR0725 # 01 Y:2019 | 01 | 2019 | MODIFY PROCESS TO REDUCE MATERIAL USE/COST | $16,581 | $12,780 | Not Implemented |
OR0717 # 02 Y:2019 | 02 | 2019 | MINIMIZE WATER USAGE | $20,973 | $587 | Not Implemented |
OR0717 # 05 Y:2019 | 05 | 2019 | RECOVER AND REUSE WASTE MATERIAL | $204,215 | $143,400 | Not Implemented |
OR0717 # 04 Y:2019 | 04 | 2019 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $2,624 | $3,273 | Not Implemented |
OR0717 # 03 Y:2019 | 03 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $14,061 | $7,650 | Not Implemented |
OR0717 # 01 Y:2019 | 01 | 2019 | USE HIGHEST TEMPERATURE FOR CHILLING OR COLD STORAGE | $1,163 | $0 | Implemented |
OR0696 # 04 Y:2017 | 04 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,910 | $10,116 | Not Implemented |
OR0696 # 03 Y:2017 | 03 | 2017 | REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | $2,365 | $5,880 | Not Implemented |
OR0696 # 02 Y:2017 | 02 | 2017 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $79,265 | $37,275 | Not Implemented |
OR0696 # 01 Y:2017 | 01 | 2017 | DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS | $179,573 | $3,044 | Not Implemented |
OR0678 # 03 Y:2016 | 03 | 2016 | INSULATE BARE EQUIPMENT | $972 | $2,626 | Implemented |
OR0678 # 02 Y:2016 | 02 | 2016 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,663 | $247 | Implemented |
OR0678 # 01 Y:2016 | 01 | 2016 | IMPROVE COMBUSTION CONTROL CAPABILITY | $4,885 | $2,948 | Not Implemented |
OR0636 # 04 Y:2014 | 04 | 2014 | REPLACE PURCHASED STEAM WITH OTHER ENERGY SOURCE | $27,166 | $37,500 | Not Implemented |