Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
235
matching recommendationsNAICS | 314 | Textile Product Mills |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WV0624 # 10 Y:2022 | 10 | 2022 | DEVELOP A REPAIR/REPLACE POLICY | $6,918 | $2,242 | Implemented |
WV0624 # 06 Y:2022 | 06 | 2022 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $33,682 | $7,000 | Implemented |
LS2105 # 05 Y:2021 | 05 | 2021 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $133 | $580 | Implemented |
LS2105 # 04 Y:2021 | 04 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,725 | $9,408 | Implemented |
LS2105 # 03 Y:2021 | 03 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,367 | $675 | Implemented |
LS2105 # 01 Y:2021 | 01 | 2021 | INSTALL TIMERS AND/OR THERMOSTATS | $1,466 | $100 | Implemented |
UA0241 # 02 Y:2021 | 02 | 2021 | INSTALL OCCUPANCY SENSORS | $2,919 | $2,696 | Implemented |
UA0241 # 04 Y:2021 | 04 | 2021 | INSTALL TIMERS AND/OR THERMOSTATS | $415 | $290 | Implemented |
UA0241 # 03 Y:2021 | 03 | 2021 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,152 | $3,309 | Implemented |
UA0241 # 01 Y:2021 | 01 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,051 | $4,640 | Implemented |
GT0931 # 07 Y:2019 | 07 | 2019 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $111 | $322 | Implemented |
GT0931 # 08 Y:2019 | 08 | 2019 | TURN OFF EQUIPMENT WHEN NOT IN USE | $34 | $131 | Implemented |
GT0931 # 05 Y:2019 | 05 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,664 | $4,500 | Implemented |
GT0931 # 03 Y:2019 | 03 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $19,194 | $25,005 | Implemented |
GT0931 # 02 Y:2019 | 02 | 2019 | INSTALL OCCUPANCY SENSORS | $2,451 | $1,382 | Implemented |
GT0931 # 01 Y:2019 | 01 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $12,292 | $3,500 | Implemented |
CL1907 # 01 Y:2019 | 01 | 2019 | PAY BILLS ON TIME TO AVOID LATE FEES | $4,250 | $4,250 | Implemented |
CL1907 # 04 Y:2019 | 04 | 2019 | INSTALL OCCUPANCY SENSORS | $1,280 | $131 | Implemented |
CL1907 # 05 Y:2019 | 05 | 2019 | KEEP DOORS AND WINDOWS SHUT WHEN NOT ON USE | $3,950 | $2,962 | Implemented |
CL1907 # 02 Y:2019 | 02 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $19,969 | $31,130 | Implemented |
GT0921 # 04 Y:2019 | 04 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $947 | $3,500 | Implemented |
GT0920 # 05 Y:2019 | 05 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,569 | $5,081 | Implemented |
GT0920 # 04 Y:2019 | 04 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,465 | $3,500 | Implemented |
GT0920 # 03 Y:2019 | 03 | 2019 | INSULATE BARE EQUIPMENT | $360 | $386 | Implemented |
GT0920 # 02 Y:2019 | 02 | 2019 | INSULATE BARE EQUIPMENT | $5,826 | $1,645 | Implemented |