Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
24
matching recommendationsNAICS | 3149 | Other Textile Product Mills |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK0784 # 02 Y:2009 | 02 | 2009 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $26,522 | $23,859 | Implemented |
OK0784 # 03 Y:2009 | 03 | 2009 | USE DRYING OVEN (BATCH TYPE) ON ALTERNATE DAYS OR OTHER OPTIMUM SCHEDULE TO RUN EQUIPMENT WITH FULL LOADS | $11,003 | $0 | Not Implemented |
OK0784 # 04 Y:2009 | 04 | 2009 | INSTALL OCCUPANCY SENSORS | $1,600 | $620 | Not Implemented |
OK0784 # 05 Y:2009 | 05 | 2009 | INSTALL OCCUPANCY SENSORS | $362 | $1,013 | Not Implemented |
OK0784 # 06 Y:2009 | 06 | 2009 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $888 | $1,098 | Not Implemented |
OK0784 # 07 Y:2009 | 07 | 2009 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,104 | $0 | Implemented |
OK0784 # 08 Y:2009 | 08 | 2009 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,788 | $0 | Implemented |
OK0784 # 09 Y:2009 | 09 | 2009 | INSTALL TIMERS AND/OR THERMOSTATS | $858 | $990 | Implemented |
OK0784 # 01 Y:2009 | 01 | 2009 | INSULATE BARE EQUIPMENT | $32,802 | $10,627 | Implemented |
MS0341 # 05 Y:2009 | 05 | 2009 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,400 | $196 | Implemented |
MS0341 # 04 Y:2009 | 04 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,747 | $15,590 | Implemented |
MS0341 # 03 Y:2009 | 03 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $16,112 | $38,096 | Implemented |
MS0341 # 02 Y:2009 | 02 | 2009 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $13,482 | $217,200 | Not Implemented |
MS0341 # 01 Y:2009 | 01 | 2009 | INSTALL DESICCANT HUMIDITY CONTROL SYSTEM | $42,353 | $102,915 | Not Implemented |
SU0278 # 06 Y:2009 | 06 | 2009 | INSTALL OCCUPANCY SENSORS | $44,212 | $7,299 | Implemented |
SU0278 # 07 Y:2009 | 07 | 2009 | INSULATE BARE EQUIPMENT | $1,289 | $1,820 | Not Implemented |
SU0278 # 08 Y:2009 | 08 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,049 | $6,721 | Implemented |
SU0278 # 09 Y:2009 | 09 | 2009 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $112 | $271 | Not Implemented |
SU0278 # 10 Y:2009 | 10 | 2009 | OPTIMIZE PLANT POWER FACTOR | $7,344 | $28,458 | Implemented |
SU0278 # 05 Y:2009 | 05 | 2009 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,615 | $410 | Implemented |
SU0278 # 04 Y:2009 | 04 | 2009 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $4,305 | $528 | Implemented |
SU0278 # 03 Y:2009 | 03 | 2009 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $8,050 | $0 | Implemented |
SU0278 # 02 Y:2009 | 02 | 2009 | USE SYNTHETIC LUBRICANT | $8,358 | $0 | Not Implemented |
SU0278 # 01 Y:2009 | 01 | 2009 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $25,359 | $0 | Implemented |