Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
22
matching recommendationsNAICS | 31499 | All Other Textile Product Mills |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AM0881 # 07 Y:2023 | 07 | 2023 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $650 | $610 | Not Implemented |
AM0881 # 06 Y:2023 | 06 | 2023 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $730 | $500 | Not Implemented |
AM0881 # 05 Y:2023 | 05 | 2023 | INSTALL OCCUPANCY SENSORS | $1,200 | $425 | Not Implemented |
AM0881 # 04 Y:2023 | 04 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,265 | $3,080 | Not Implemented |
AM0881 # 03 Y:2023 | 03 | 2023 | OPTIMIZE PLANT POWER FACTOR | $4,840 | $6,780 | Not Implemented |
AM0881 # 02 Y:2023 | 02 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,050 | $1,000 | Not Implemented |
AM0881 # 01 Y:2023 | 01 | 2023 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $22,165 | $0 | Not Implemented |
AM0674 # 02 Y:2015 | 02 | 2015 | OPTIMIZE PLANT POWER FACTOR | $4,070 | $3,950 | Not Implemented |
AM0674 # 09 Y:2015 | 09 | 2015 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $430 | $0 | Not Implemented |
AM0674 # 08 Y:2015 | 08 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $550 | $275 | Implemented |
AM0674 # 07 Y:2015 | 07 | 2015 | INSTALL SKYLIGHTS | $625 | $970 | Not Implemented |
AM0674 # 06 Y:2015 | 06 | 2015 | INSULATE FEEDWATER TANK | $950 | $140 | Not Implemented |
AM0674 # 05 Y:2015 | 05 | 2015 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,185 | $500 | Implemented |
AM0674 # 04 Y:2015 | 04 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,420 | $5 | Not Implemented |
AM0674 # 03 Y:2015 | 03 | 2015 | REPAIR OR REPLACE STEAM TRAPS | $2,350 | $440 | Implemented |
AM0674 # 01 Y:2015 | 01 | 2015 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $23,350 | $24,500 | Not Implemented |
TA0056 # 01 Y:2003 | 01 | 2003 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE HANDLING COSTS | $190,000 | $141,875 | Not Implemented |
TA0056 # 02 Y:2003 | 02 | 2003 | OPTIMIZE PRODUCTION LOT SIZES AND INVENTORIES | $13,500 | $1,075 | Not Implemented |
TA0056 # 03 Y:2003 | 03 | 2003 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $6,726 | $0 | Implemented |
TA0056 # 04 Y:2003 | 04 | 2003 | INSTALL TIMERS AND/OR THERMOSTATS | $880 | $325 | Implemented |
TA0056 # 05 Y:2003 | 05 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $770 | $0 | Implemented |
TA0056 # 06 Y:2003 | 06 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $710 | $1,128 | Implemented |