IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

46

matching recommendations
Reset
NAICS 3211 Sawmills and Wood Preservation
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
LE0519 # 02 Y:2022 02 2022 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,106 $1,000 Implemented
LE0519 # 03 Y:2022 03 2022 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $48,358 $85,000 Not Implemented
LE0519 # 04 Y:2022 04 2022 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $835 $1,670 Implemented
LE0519 # 05 Y:2022 05 2022 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $6,082 $16,800 Implemented
LE0519 # 06 Y:2022 06 2022 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $14,038 $57,000 Not Implemented
LE0519 # 01 Y:2022 01 2022 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $971 $25 Implemented
LE0338 # 13 Y:2012 13 2012 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,134 $200 Implemented
LE0338 # 11 Y:2012 11 2012 INSTALL TIMERS AND/OR THERMOSTATS $2,293 $100 Implemented
LE0338 # 12 Y:2012 12 2012 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,635 $8,000 Implemented
LE0338 # 08 Y:2012 08 2012 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $4,115 $16,500 Not Implemented
LE0338 # 07 Y:2012 07 2012 PREHEAT COMBUSTION AIR WITH WASTE HEAT $6,563 $16,000 Implemented
LE0338 # 05 Y:2012 05 2012 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $11,074 $10,000 Implemented
LE0338 # 14 Y:2012 14 2012 INSTALL / REPAIR INSULATION ON STEAM LINES $330 $103 Implemented
LE0338 # 03 Y:2012 03 2012 REPAIR OR REPLACE STEAM TRAPS $23,903 $1,800 Implemented
LE0338 # 09 Y:2012 09 2012 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,773 $1,000 Implemented
LE0338 # 01 Y:2012 01 2012 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $38,956 $30,500 Implemented
LE0338 # 06 Y:2012 06 2012 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $7,332 $500 Implemented
LE0338 # 02 Y:2012 02 2012 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $27,600 $20,000 Implemented
LE0338 # 10 Y:2012 10 2012 INSTALL OCCUPANCY SENSORS $2,166 $1,050 Implemented
LE0338 # 04 Y:2012 04 2012 PREHEAT COMBUSTION AIR WITH WASTE HEAT $15,000 $0 Not Implemented
SU0246 # 01 Y:2007 01 2007 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $4,554 $0 Implemented
SU0246 # 02 Y:2007 02 2007 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $3,404 $0 Implemented
SU0246 # 03 Y:2007 03 2007 USE SYNTHETIC LUBRICANT $2,489 $0 Implemented
SU0246 # 05 Y:2007 05 2007 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,989 $42 Implemented
SU0246 # 06 Y:2007 06 2007 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,230 $850 Implemented