Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
708
matching recommendationsNAICS | 321113 | Sawmills |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0577 # 06 Y:2012 | 06 | 2012 | KEEP SOLID FUELS / RAW MATERIALS DRY | $12,037 | $50,000 | Implemented |
CO0652 # 01 Y:2011 | 01 | 2011 | INSTALL EQUIPMENT TO UTILIZE WASTE FUEL | $11,990 | $34,320 | Implemented |
CO0652 # 02 Y:2011 | 02 | 2011 | CHANGE PRODUCT DESIGN TO REDUCE ENERGY REQUIREMENTS | $7,570 | $13,550 | Not Implemented |
CO0652 # 03 Y:2011 | 03 | 2011 | USE SOLAR HEAT TO HEAT MAKE-UP AIR | $7,530 | $35,420 | Not Implemented |
CO0652 # 04 Y:2011 | 04 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,100 | $870 | Implemented |
CO0648 # 01 Y:2011 | 01 | 2011 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $5,240 | $34,900 | Not Implemented |
CO0648 # 02 Y:2011 | 02 | 2011 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,210 | $6,130 | Not Implemented |
CO0648 # 03 Y:2011 | 03 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,780 | $410 | Implemented |
CO0648 # 04 Y:2011 | 04 | 2011 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $270 | $400 | Not Implemented |
CO0648 # 05 Y:2011 | 05 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $600 | $2,710 | Not Implemented |
CO0647 # 01 Y:2011 | 01 | 2011 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,240 | $5,950 | Not Implemented |
CO0647 # 02 Y:2011 | 02 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,490 | $520 | Implemented |
CO0647 # 03 Y:2011 | 03 | 2011 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $950 | $600 | Implemented |
CO0647 # 04 Y:2011 | 04 | 2011 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $790 | $1,410 | Not Implemented |
CO0647 # 05 Y:2011 | 05 | 2011 | USE SOLAR HEAT TO MAKE ELECTRICTY | $2,420 | $27,500 | Not Implemented |
WV0432 # 01 Y:2011 | 01 | 2011 | INSTALL EQUIPMENT TO UTILIZE WASTE FUEL | $101,575 | $193,750 | Not Implemented |
WV0432 # 02 Y:2011 | 02 | 2011 | OPTIMIZE PLANT POWER FACTOR | $4,812 | $10,750 | Not Implemented |
WV0432 # 03 Y:2011 | 03 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,660 | $3,828 | Not Implemented |
WV0432 # 04 Y:2011 | 04 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,762 | $290 | Implemented |
WV0432 # 05 Y:2011 | 05 | 2011 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $2,144 | $2,000 | Implemented |
WV0432 # 06 Y:2011 | 06 | 2011 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $1,989 | $16,000 | Not Implemented |
WV0432 # 07 Y:2011 | 07 | 2011 | DEVELOP A REPAIR/REPLACE POLICY | $1,677 | $1,775 | Implemented |
WV0432 # 08 Y:2011 | 08 | 2011 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,014 | $1,425 | Not Implemented |
WV0432 # 09 Y:2011 | 09 | 2011 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $873 | $1,000 | Not Implemented |
WV0432 # 10 Y:2011 | 10 | 2011 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $762 | $1,000 | Implemented |