Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,548
matching recommendationsNAICS | 3219 | Other Wood Product Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LM0114 # 01 Y:2006 | 01 | 2006 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $2,544 | $0 | Implemented |
LM0114 # 02 Y:2006 | 02 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $11,286 | $9,409 | Not Implemented |
LM0114 # 03 Y:2006 | 03 | 2006 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $811 | $0 | Implemented |
LM0114 # 04 Y:2006 | 04 | 2006 | TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY | $175,670 | $14,400 | Not Implemented |
LM0114 # 05 Y:2006 | 05 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,671 | $200 | Implemented |
BD0310 # 01 Y:2006 | 01 | 2006 | USE RADIANT HEATER FOR SPOT HEATING | $4,173 | $2 | Implemented |
BD0310 # 02 Y:2006 | 02 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,537 | $600 | Implemented |
BD0310 # 03 Y:2006 | 03 | 2006 | USE SYNTHETIC LUBRICANT | $805 | $300 | Implemented |
BD0310 # 04 Y:2006 | 04 | 2006 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $577 | $0 | Not Implemented |
BD0310 # 05 Y:2006 | 05 | 2006 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $267 | $500 | Implemented |
BD0310 # 06 Y:2006 | 06 | 2006 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,368 | $90 | Implemented |
BD0310 # 07 Y:2006 | 07 | 2006 | INSTALL OCCUPANCY SENSORS | $288 | $225 | Not Implemented |
BD0310 # 08 Y:2006 | 08 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $240 | $250 | Implemented |
AS0413 # 01 Y:2006 | 01 | 2006 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $21,882 | $1,000 | Implemented |
AS0413 # 02 Y:2006 | 02 | 2006 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $18,423 | $15,000 | Implemented |
AS0413 # 03 Y:2006 | 03 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $16,455 | $15,000 | Implemented |
MA0595 # 01 Y:2006 | 01 | 2006 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $32,853 | $158,280 | Not Implemented |
MA0595 # 02 Y:2006 | 02 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,311 | $27,000 | Implemented |
MA0595 # 03 Y:2006 | 03 | 2006 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $5,019 | $8,507 | Not Implemented |
MA0595 # 04 Y:2006 | 04 | 2006 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $935 | $0 | Implemented |
MA0595 # 05 Y:2006 | 05 | 2006 | INSULATE BARE EQUIPMENT | $62 | $150 | Implemented |
MI0122 # 01 Y:2006 | 01 | 2006 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $18,965 | $5,163 | Not Implemented |
MI0122 # 02 Y:2006 | 02 | 2006 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $15,874 | $3,709 | Not Implemented |
MI0122 # 03 Y:2006 | 03 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,318 | $1,074 | Not Implemented |
MI0122 # 04 Y:2006 | 04 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,569 | $1,074 | Not Implemented |