Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oregon State University |
---|---|
Assessment Year | 2006 |
Principal Product | doors and Molding |
NAICS | 321911 - Wood Window and Door Manufacturing |
SIC | 2431 - Millwork |
Sales | $10,000,000-$50,000,000 |
# of Employees | 350 |
Plant Area (Sq.Ft.) | 300,000 |
Annual Production | 315,000 Pieces |
Production Hrs. Annual | 4,500 |
Location (State) | OR |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $167,125 | 4,964,320 | kWh | $0.03 |
Electricity Demand | $60 | 2 | kW-months/year | $30.00 |
Natural Gas | $166,086 | 13,419 | MMBtu | $12.38 |
TOTAL ENERGY COSTS | $333,271 | |||
RECOMMENDED SAVINGS* | $268,930 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $191,770 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED |
Savings: $18,900 Cost: - |
$12,200 | 338,100 | $6,700 | 6,700 | - | - | - | - | - | - |
$12,200 338,100 kWh |
$6,700 6,700 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS |
Savings: $4,600 Cost: - |
$4,600 | 127,000 | - | - | - | - | - | - | - | - |
$4,600 127,000 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $5,000 Cost: - |
$3,900 | 115,000 | $1,100 | 4 | - | - | - | - | - | - |
$3,900 115,000 kWh |
$1,100 4 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $6,300 Cost: $600 |
- | - | - | - | $6,300 | 557 | - | - | - | - |
- - kWh |
- - kW-months/year |
$6,300 557 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4226 USE / PURCHASE OPTIMUM SIZED COMPRESSOR |
Savings: $36,760 Cost: $2,700 |
$36,760 | 798 | - | - | - | - | - | - | - | - |
$36,760 798 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4322 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES |
Savings: $17,000 Cost: $8,000 |
$17,000 | 342 | - | - | - | - | - | - | - | - |
$17,000 342 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,000 Cost: $1,000 |
$900 | 24 | $100 | 3 | - | - | - | - | - | - |
$900 24 kWh |
$100 3 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.5195 CHANGE PRODUCT DESIGN TO REDUCE ENERGY REQUIREMENTS |
Savings: $168,270 Cost: $185,000 |
$16,480 | 111,600 | $4,040 | 314 | - | - | $420,000 | - | $(-272,250) | - |
$16,480 111,600 kWh |
$4,040 314 kW-months/year |
- - MMBtu |
$420,000 - $ |
$(-272,250) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $11,100 Cost: $32,300 |
$8,500 | 234 | $2,600 | 49 | - | - | - | - | - | - |
$8,500 234 kWh |
$2,600 49 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $268,930 Cost: $229,600 |
$100,340 | 693,098 | $14,540 | 7,070 | $6,300 | 557 | $420,000 | - | $(-272,250) | - | $100,340 693,098 kWh |
$14,540 7,070 kW-months/year |
$6,300 557 MMBtu |
$420,000 - $ |
$(-272,250) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $191,770 Cost: $185,000 |
$33,280 | 576,700 | $10,740 | 7,014 | - | - | $420,000 | - | $(-272,250) | - | $33,280 576,700 kWh |
$10,740 7,014 kW-months/year |
- - MMBtu |
$420,000 - $ |
$(-272,250) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost |