Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
219
matching recommendationsNAICS | 32199 | All Other Wood Product Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LE0365 # 03 Y:2013 | 03 | 2013 | INSTALL OCCUPANCY SENSORS | $435 | $1,950 | Implemented |
LE0365 # 05 Y:2013 | 05 | 2013 | INSTALL TIMERS AND/OR THERMOSTATS | $1,398 | $115 | Implemented |
LE0365 # 07 Y:2013 | 07 | 2013 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,158 | $5,700 | Implemented |
LE0365 # 08 Y:2013 | 08 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $514 | $1,000 | Implemented |
LE0365 # 09 Y:2013 | 09 | 2013 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $280 | $300 | Implemented |
LE0365 # 10 Y:2013 | 10 | 2013 | INSTALL OCCUPANCY SENSORS | $4,529 | $1,172 | Implemented |
LE0365 # 12 Y:2013 | 12 | 2013 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,729 | $8,300 | Implemented |
TT0109 # 01 Y:2013 | 01 | 2013 | ADJUST BURNERS FOR EFFICIENT OPERATION | $3,611 | $50 | Implemented |
TT0109 # 03 Y:2013 | 03 | 2013 | UPGRADE CONTROLS ON COMPRESSORS | $7,651 | $25 | Implemented |
TT0109 # 04 Y:2013 | 04 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,206 | $63 | Implemented |
TT0109 # 05 Y:2013 | 05 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,030 | $20,000 | Implemented |
TT0109 # 06 Y:2013 | 06 | 2013 | APPLY FOR INVESTMENT INCENTIVES | $2,271 | $0 | Implemented |
NC0478 # 04 Y:2013 | 04 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $557 | $1,410 | Implemented |
NC0478 # 05 Y:2013 | 05 | 2013 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $489 | $0 | Implemented |
NC0478 # 06 Y:2013 | 06 | 2013 | TURN OFF EQUIPMENT WHEN NOT IN USE | $3,874 | $1,800 | Implemented |
NC0478 # 08 Y:2013 | 08 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $219 | $200 | Implemented |
NC0478 # 09 Y:2013 | 09 | 2013 | DEVELOP A REPAIR/REPLACE POLICY | $4,732 | $10,912 | Implemented |
UK1216 # 01 Y:2013 | 01 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,607 | $4,607 | Implemented |
UK1216 # 02 Y:2013 | 02 | 2013 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $2,150 | $1,000 | Implemented |
UK1216 # 03 Y:2013 | 03 | 2013 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $145,660 | $993,792 | Implemented |
UK1216 # 04 Y:2013 | 04 | 2013 | REPAIR AND ELIMINATE STEAM LEAKS | $31,294 | $26,400 | Implemented |
TT0104 # 02 Y:2013 | 02 | 2013 | INSTALL OCCUPANCY SENSORS | $13,653 | $5,720 | Implemented |
TT0104 # 03 Y:2013 | 03 | 2013 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $8,455 | $13,594 | Implemented |
MA0702 # 01 Y:2012 | 01 | 2012 | REDUCE FLUID FLOW RATES | $11,375 | $9,400 | Implemented |
MA0702 # 02 Y:2012 | 02 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,144 | $1,500 | Implemented |