IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

2,915

matching recommendations
Reset
NAICS 322 Paper Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UA3009 # 07 Y:2011 07 2011 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $15,274 $5,000 Implemented
UA3009 # 08 Y:2011 08 2011 USE FLUE GASES TO HEAT PROCESS OR SERVICE WATER $22,812 $64,000 Not Implemented
UA3009 # 09 Y:2011 09 2011 INSULATE BARE EQUIPMENT $7,844 $1,950 Not Implemented
UA3009 # 10 Y:2011 10 2011 METER WASTE WATER $55,751 $7,500 n/a
BD0376 # 01 Y:2010 01 2010 REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES $105,011 $51,500 Implemented
BD0376 # 02 Y:2010 02 2010 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $67,200 $125 Not Implemented
BD0376 # 03 Y:2010 03 2010 RECOVER WASTE HEAT FROM EQUIPMENT $62,913 $70,000 Implemented
BD0376 # 04 Y:2010 04 2010 RECOVER WASTE HEAT FROM EQUIPMENT $39,238 $34,000 Implemented
BD0376 # 05 Y:2010 05 2010 INSTALL TURBULATORS $20,378 $4,350 Not Implemented
BD0376 # 06 Y:2010 06 2010 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $11,590 $5,500 Implemented
BD0376 # 07 Y:2010 07 2010 USE RADIANT HEATER FOR SPOT HEATING $7,210 $9,000 Not Implemented
BD0376 # 08 Y:2010 08 2010 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $989 $1,727 Implemented
SD0430 # 01 Y:2010 01 2010 UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT $264 $0 Not Implemented
SD0430 # 02 Y:2010 02 2010 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,152 $100 Not Implemented
SD0430 # 03 Y:2010 03 2010 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,949 $800 Implemented
SD0430 # 04 Y:2010 04 2010 INSTALL OCCUPANCY SENSORS $1,126 $1,029 Not Implemented
SD0430 # 05 Y:2010 05 2010 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,250 $1,671 Not Implemented
OK0797 # 01 Y:2010 01 2010 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $340 $236 Not Implemented
OK0797 # 02 Y:2010 02 2010 RECOVER WASTE HEAT FROM EQUIPMENT $1,606 $402 Not Implemented
OK0797 # 03 Y:2010 03 2010 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,987 $1,500 Implemented
OK0797 # 04 Y:2010 04 2010 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $718 $1,654 Not Implemented
OK0797 # 05 Y:2010 05 2010 INSTALL OCCUPANCY SENSORS $260 $0 Implemented
OK0797 # 06 Y:2010 06 2010 INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT $583 $2,539 Not Implemented
OK0797 # 07 Y:2010 07 2010 INSTALL SET-BACK TIMERS $14,118 $5,326 Not Implemented
OK0797 # 08 Y:2010 08 2010 INSTALL SET-BACK TIMERS $3,991 $3,994 Not Implemented