matching recommendationsNAICS | 32212 | Paper Mills |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
BD0326 # 06 Y:2007 | 06 | 2007 | RECOVER WASTE HEAT FROM EQUIPMENT | $9,125 | $1,200 | Not Implemented |
BD0326 # 07 Y:2007 | 07 | 2007 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $14,867 | $5,500 | Not Implemented |
BD0326 # 08 Y:2007 | 08 | 2007 | MODIFY STARTUP/SHUTDOWN TIMES | $2,400 | $7,000 | Not Implemented |
BD0326 # 09 Y:2007 | 09 | 2007 | RECOVER AND REUSE WASTE MATERIAL | $512 | $0 | Not Implemented |
BD0326 # 10 Y:2007 | 10 | 2007 | REPAIR AND ELIMINATE STEAM LEAKS | $270 | $150 | Not Implemented |
SU0253 # 01 Y:2007 | 01 | 2007 | USE SYNTHETIC LUBRICANT | $10,167 | $0 | Implemented |
SU0253 # 02 Y:2007 | 02 | 2007 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $7,378 | $0 | Implemented |
SU0253 # 03 Y:2007 | 03 | 2007 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,268 | $0 | Implemented |
SU0253 # 04 Y:2007 | 04 | 2007 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $19,715 | $2,349 | Implemented |
SU0253 # 05 Y:2007 | 05 | 2007 | REPAIR AND ELIMINATE STEAM LEAKS | $6,121 | $66 | Implemented |
SU0253 # 06 Y:2007 | 06 | 2007 | INSTALL / REPAIR INSULATION ON STEAM LINES | $2,143 | $542 | Implemented |
SU0253 # 07 Y:2007 | 07 | 2007 | INSTALL / REPAIR INSULATION ON STEAM LINES | $545 | $185 | Implemented |
SU0253 # 08 Y:2007 | 08 | 2007 | PREHEAT COMBUSTION AIR WITH WASTE HEAT | $67,711 | $37,811 | Not Implemented |
SU0253 # 09 Y:2007 | 09 | 2007 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $46,500 | $34,295 | Implemented |
SU0253 # 10 Y:2007 | 10 | 2007 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $311 | $543 | Implemented |
SU0253 # 11 Y:2007 | 11 | 2007 | OPTIMIZE PLANT POWER FACTOR | $15,304 | $45,129 | Not Implemented |
SU0253 # 12 Y:2007 | 12 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,364 | $16,006 | Implemented |
SU0252 # 01 Y:2007 | 01 | 2007 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $9,856 | $0 | Implemented |
SU0252 # 02 Y:2007 | 02 | 2007 | USE SYNTHETIC LUBRICANT | $9,114 | $0 | Implemented |
SU0252 # 03 Y:2007 | 03 | 2007 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $8,725 | $0 | Not Implemented |
SU0252 # 04 Y:2007 | 04 | 2007 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,543 | $901 | Implemented |
SU0252 # 05 Y:2007 | 05 | 2007 | REPAIR AND ELIMINATE STEAM LEAKS | $6,404 | $134 | Implemented |
SU0252 # 06 Y:2007 | 06 | 2007 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $4,230 | $444 | Implemented |
SU0252 # 07 Y:2007 | 07 | 2007 | INSTALL / REPAIR INSULATION ON STEAM LINES | $3,867 | $788 | Implemented |
SU0252 # 08 Y:2007 | 08 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $11,800 | $19,800 | Implemented |