IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

57

matching recommendations
Reset
NAICS 32221 Paperboard Container Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
SU0452 # 04 Y:2017 04 2017 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $347 $524 Implemented
SU0452 # 05 Y:2017 05 2017 UPGRADE OBSOLETE EQUIPMENT $25,555 $120,000 Implemented
SU0452 # 01 Y:2017 01 2017 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $4,109 $0 Implemented
SU0452 # 03 Y:2017 03 2017 ELIMINATE/REDUCE AN OPERATION $16,784 $4,317 Implemented
SU0352 # 05 Y:2013 05 2013 INSTALL OCCUPANCY SENSORS $743 $498 Implemented
SU0352 # 06 Y:2013 06 2013 INSTALL / REPAIR INSULATION ON STEAM LINES $1,473 $1,292 Implemented
SU0352 # 04 Y:2013 04 2013 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $628 $290 Implemented
SU0334 # 10 Y:2013 10 2013 REPLACE BOILER $945 $4,440 Implemented
SU0334 # 06 Y:2013 06 2013 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $464 $170 Implemented
SU0334 # 05 Y:2013 05 2013 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $831 $307 Implemented
SU0334 # 04 Y:2013 04 2013 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS $555 $139 Implemented
SU0334 # 03 Y:2013 03 2013 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $648 $0 Implemented
SU0334 # 11 Y:2013 11 2013 PAY BILLS ON TIME TO AVOID LATE FEES $450 $0 Implemented
SU0334 # 07 Y:2013 07 2013 INSTALL / REPAIR INSULATION ON STEAM LINES $212 $393 Implemented
SU0334 # 02 Y:2013 02 2013 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $799 $0 Implemented
SU0326 # 02 Y:2012 02 2012 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $8,393 $2,291 Implemented
SU0326 # 07 Y:2012 07 2012 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,280 $3,077 Implemented
SU0326 # 01 Y:2012 01 2012 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $5,463 $0 Implemented
SU0326 # 03 Y:2012 03 2012 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $148 $59 Implemented
SU0326 # 09 Y:2012 09 2012 INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS $61,559 $262,789 Implemented
SU0269 # 03 Y:2008 03 2008 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $527 $0 Implemented
SU0269 # 04 Y:2008 04 2008 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,164 $198 Implemented
SU0269 # 05 Y:2008 05 2008 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,485 $209 Implemented
SU0269 # 06 Y:2008 06 2008 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,570 $333 Implemented
SU0269 # 07 Y:2008 07 2008 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $3,786 $2,539 Implemented