IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

90

matching recommendations
Reset
NAICS 32221 Paperboard Container Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UF0612 # 01 Y:2024 01 2024 USE WASTE HEAT WITH A CLOSED-CYCLE GAS TURBINE-GENERATOR SET TO COGENERATE ELECTRICITY AND HEAT $402,389 $1,529,500 n/a
UF0612 # 03 Y:2024 03 2024 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $45,994 $20,000 n/a
UF0612 # 10 Y:2024 10 2024 METER RECYCLED WATER (TO REDUCE SEWER CHARGES) $5,066 $2,320 n/a
UF0612 # 09 Y:2024 09 2024 UPGRADE CONTROLS ON COMPRESSORS $5,236 $6,087 n/a
UF0612 # 08 Y:2024 08 2024 MINIMIZE CONDENSER COOLING WATER TEMPERATURE $7,481 $5,900 n/a
UF0612 # 02 Y:2024 02 2024 USE DEMAND CONTROLLER OR LOAD SHEDDER $55,068 $30,945 n/a
UF0612 # 04 Y:2024 04 2024 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $44,735 $34,020 n/a
UF0612 # 05 Y:2024 05 2024 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $13,865 $8,523 n/a
UF0612 # 06 Y:2024 06 2024 INSTALL TURBULATORS $13,749 $3,750 n/a
UF0612 # 07 Y:2024 07 2024 INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS $9,443 $21,120 n/a
UF0403 # 06 Y:2007 06 2007 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $2,878 $251 Implemented
UF0403 # 12 Y:2007 12 2007 INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS $10,940 $6,812 Not Implemented
UF0403 # 10 Y:2007 10 2007 INSTALL SET-BACK TIMERS $1,702 $159 Implemented
UF0403 # 09 Y:2007 09 2007 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $55,813 $24,509 Not Implemented
UF0403 # 07 Y:2007 07 2007 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,932 $507 Implemented
UF0403 # 14 Y:2007 14 2007 OPTIMIZE PLANT POWER FACTOR $56,662 $10,350 Not Implemented
UF0403 # 05 Y:2007 05 2007 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $1,880 $184 Implemented
UF0403 # 02 Y:2007 02 2007 UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT $266 $144 Implemented
UF0403 # 13 Y:2007 13 2007 INSTALL TIMERS AND/OR THERMOSTATS $11,252 $1,631 Not Implemented
UF0403 # 01 Y:2007 01 2007 USE PHOTOCELL CONTROLS $3,552 $792 Implemented
UF0403 # 08 Y:2007 08 2007 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $1,592 $5,607 Not Implemented
UF0403 # 03 Y:2007 03 2007 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $23,512 $74,284 Not Implemented
UF0403 # 04 Y:2007 04 2007 INSTALL OCCUPANCY SENSORS $307 $444 Not Implemented
UF0403 # 15 Y:2007 15 2007 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $820 $3,486 Not Implemented
UF0403 # 11 Y:2007 11 2007 USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE $14,757 $25,340 Not Implemented