Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
75
matching recommendationsNAICS | 322211 | Corrugated and Solid Fiber Box Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IC0102 # 14 Y:2005 | 14 | 2005 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $10,924 | $2,500 | Not Implemented |
IC0102 # 16 Y:2005 | 16 | 2005 | DISCONNECT BALLASTS | $29,539 | $2,208 | Not Implemented |
IC0102 # 15 Y:2005 | 15 | 2005 | UPGRADE CONTROLS ON COMPRESSORS | $669 | $168 | Not Implemented |
IC0102 # 11 Y:2005 | 11 | 2005 | CHECK FOR ACCURACY OF UTILITY / POWER METERS | $10,135 | $10,152 | Not Implemented |
IC0102 # 12 Y:2005 | 12 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,208 | $5,000 | Not Implemented |
IC0102 # 13 Y:2005 | 13 | 2005 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,019 | $220 | Not Implemented |
IC0102 # 09 Y:2005 | 09 | 2005 | KEEP BOILER TUBES CLEAN | $3,862 | $776 | Not Implemented |
BD0288 # 01 Y:2005 | 01 | 2005 | INSTALL REPLACEMENT DOORS | $65,227 | $72,000 | Implemented |
BD0288 # 02 Y:2005 | 02 | 2005 | USE RADIANT HEATER FOR SPOT HEATING | $13,106 | $12,800 | Not Implemented |
BD0288 # 03 Y:2005 | 03 | 2005 | REPLACE BOILER | $14,342 | $2,500 | Implemented |
BD0288 # 04 Y:2005 | 04 | 2005 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $8,812 | $900 | Implemented |
BD0288 # 05 Y:2005 | 05 | 2005 | IMPROVE COMBUSTION CONTROL CAPABILITY | $5,194 | $2,000 | Implemented |
BD0288 # 06 Y:2005 | 06 | 2005 | USE SYNTHETIC LUBRICANT | $536 | $550 | Implemented |
BD0288 # 07 Y:2005 | 07 | 2005 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $4,293 | $10,160 | Implemented |
BD0288 # 08 Y:2005 | 08 | 2005 | REPAIR AND ELIMINATE STEAM LEAKS | $2,844 | $2,400 | Implemented |
BD0288 # 09 Y:2005 | 09 | 2005 | RECOVER WASTE HEAT FROM EQUIPMENT | $712 | $1,000 | Not Implemented |
BD0288 # 10 Y:2005 | 10 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,050 | $300 | Implemented |
BD0288 # 11 Y:2005 | 11 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,154 | $2,480 | Not Implemented |
BD0288 # 12 Y:2005 | 12 | 2005 | INSTALL OCCUPANCY SENSORS | $677 | $375 | Implemented |
BD0288 # 13 Y:2005 | 13 | 2005 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $1,651 | $1,250 | Not Implemented |
IC0055 # 07 Y:2003 | 07 | 2003 | REPAIR AND ELIMINATE STEAM LEAKS | $5,069 | $2,100 | Implemented |
IC0055 # 08 Y:2003 | 08 | 2003 | REDUCE SCRAP PRODUCTION | $130 | $0 | Not Implemented |
IC0055 # 09 Y:2003 | 09 | 2003 | AUTOMATE PAYROLL SYSTEM | $36,930 | $11,045 | Not Implemented |
IC0055 # 06 Y:2003 | 06 | 2003 | CONVERT FROM INDIRECT TO DIRECT FIRED SYSTEMS | $9,243 | $61,200 | Not Implemented |
IC0055 # 05 Y:2003 | 05 | 2003 | INSTALL / REPAIR INSULATION ON STEAM LINES | $417 | $454 | Not Implemented |