Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
229
matching recommendationsNAICS | 32229 | Other Converted Paper Product Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
CO0660 # 01 Y:2012 | 01 | 2012 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $510 | $3,090 | Implemented |
CO0660 # 02 Y:2012 | 02 | 2012 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $2,610 | $500 | Implemented |
CO0660 # 03 Y:2012 | 03 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,410 | $3,310 | Not Implemented |
WM0003 # 01 Y:2012 | 01 | 2012 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,254 | $600 | Implemented |
WM0003 # 02 Y:2012 | 02 | 2012 | INSTALL OCCUPANCY SENSORS | $2,091 | $0 | Not Implemented |
WM0003 # 03 Y:2012 | 03 | 2012 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $2,223 | $0 | Not Implemented |
WM0003 # 04 Y:2012 | 04 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $226 | $120 | Implemented |
WM0003 # 05 Y:2012 | 05 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $137 | $360 | Implemented |
WM0003 # 06 Y:2012 | 06 | 2012 | CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS | $493 | $99 | Not Implemented |
WM0003 # 07 Y:2012 | 07 | 2012 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $2,160 | $900 | Not Implemented |
DL0070 # 01 Y:2011 | 01 | 2011 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $136,635 | $120,000 | Implemented |
DL0070 # 02 Y:2011 | 02 | 2011 | REDUCE VENTILATION AIR | $12,200 | $200 | Implemented |
DL0070 # 03 Y:2011 | 03 | 2011 | REDUCE VENTILATION AIR | $2,160 | $45 | Not Implemented |
DL0070 # 04 Y:2011 | 04 | 2011 | MINIMIZE OPERATION OF EQUIPMENT MAINTAINED IN STANDBY CONDITION | $14,330 | $500 | Implemented |
DL0070 # 05 Y:2011 | 05 | 2011 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,782 | $1,800 | Not Implemented |
DL0070 # 06 Y:2011 | 06 | 2011 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $104,177 | $157,000 | Implemented |
DL0070 # 07 Y:2011 | 07 | 2011 | USE STEAM SPARGING OR INJECTIONS IN PLACE OF INDIRECT HEATING | $4,600 | $10,000 | Not Implemented |
DL0070 # 08 Y:2011 | 08 | 2011 | MODERATE COOLING TOWER OUTLET TEMPERATURE | $21,528 | $52,000 | Implemented |
DL0070 # 09 Y:2011 | 09 | 2011 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $4,701 | $10,500 | Not Implemented |
DL0070 # 10 Y:2011 | 10 | 2011 | USE SOLAR HEAT TO MAKE ELECTRICTY | $33,730 | $1,035,000 | Not Implemented |
LE0316 # 01 Y:2011 | 01 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $37,608 | $67,275 | Not Implemented |
LE0316 # 02 Y:2011 | 02 | 2011 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $13,225 | $11,500 | Not Implemented |
LE0316 # 03 Y:2011 | 03 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $12,035 | $13,000 | Not Implemented |
LE0316 # 04 Y:2011 | 04 | 2011 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $7,994 | $3,000 | Not Implemented |
LE0316 # 05 Y:2011 | 05 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,230 | $25,000 | Not Implemented |