IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

28

matching recommendations
Reset
NAICS 323111 Commercial Printing (except Screen and Books)
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
NL0017 # 03 Y:2018 03 2018 USE FLOW CONTROL VALVES ON EQUIPMENT TO OPTIMIZE WATER USE $2,784 $275 Not Implemented
NL0017 # 02 Y:2018 02 2018 METER RECYCLED WATER (TO REDUCE SEWER CHARGES) $12,800 $2,000 Implemented
NL0017 # 01 Y:2018 01 2018 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $16,615 $60,000 Implemented
IA0502 # 07 Y:2013 07 2013 TURN OFF EQUIPMENT WHEN NOT IN USE $1,147 $205 Implemented
IA0502 # 06 Y:2013 06 2013 INSTALL OCCUPANCY SENSORS $631 $3,164 Implemented
IA0502 # 05 Y:2013 05 2013 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $629 $700 Not Implemented
IA0502 # 04 Y:2013 04 2013 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $796 $155 Implemented
IA0502 # 03 Y:2013 03 2013 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $1,859 $205 Implemented
IA0502 # 02 Y:2013 02 2013 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,777 $405 Implemented
IA0502 # 01 Y:2013 01 2013 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $23,996 $37,758 Implemented
IA0342 # 03 Y:2004 03 2004 INSTALL OCCUPANCY SENSORS $1,094 $888 Implemented
IA0342 # 06 Y:2004 06 2004 MODIFY PROCESS TO REDUCE MATERIAL USE/COST $7,150 $715 Implemented
IA0342 # 05 Y:2004 05 2004 TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY $10,625 $538 Not Implemented
IA0342 # 04 Y:2004 04 2004 MINIMIZE USE OF OUTSIDE MAKE-UP AIR FOR VENTILATION EXCEPT WHEN USED FOR ECONOMIZER CYCLE $1,701 $1,500 Implemented
IA0342 # 02 Y:2004 02 2004 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $8,335 $31,871 Not Implemented
IA0342 # 01 Y:2004 01 2004 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $775 $344 Implemented
IA0338 # 06 Y:2004 06 2004 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $74,749 $162,500 Implemented
IA0338 # 05 Y:2004 05 2004 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $462 $0 Implemented
IA0338 # 04 Y:2004 04 2004 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,854 $5,572 Implemented
IA0338 # 03 Y:2004 03 2004 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $895 $2,750 Implemented
IA0338 # 02 Y:2004 02 2004 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,036 $20 Implemented
IA0338 # 01 Y:2004 01 2004 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $457 $189 Implemented
IA0334 # 01 Y:2004 01 2004 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $7,614 $583 Implemented
IA0334 # 06 Y:2004 06 2004 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $267,824 $500,000 Not Implemented
IA0334 # 05 Y:2004 05 2004 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $1,196 $664 Implemented