Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
54
matching recommendationsNAICS | 323111 | Commercial Printing (except Screen and Books) |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UF0332 # 05 Y:2003 | 05 | 2003 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,090 | $1,060 | Implemented |
UF0332 # 01 Y:2003 | 01 | 2003 | INSTALL DESICCANT HUMIDITY CONTROL SYSTEM | $20,678 | $12,800 | Not Implemented |
UF0332 # 02 Y:2003 | 02 | 2003 | REPLACE HEAT TREATING OVEN WITH MORE EFFICIENT UNIT | $15,627 | $1,500 | Not Implemented |
UF0332 # 03 Y:2003 | 03 | 2003 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $676 | $803 | Implemented |
UF0332 # 04 Y:2003 | 04 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,350 | $4,928 | Not Implemented |
UF0332 # 06 Y:2003 | 06 | 2003 | PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST | $6,954 | $42,000 | Implemented |
UU0052 # 07 Y:2003 | 07 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $392 | $594 | n/a |
UU0052 # 09 Y:2003 | 09 | 2003 | RECOVER AND REUSE WASTE MATERIAL | $50 | $0 | n/a |
UU0052 # 08 Y:2003 | 08 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,664 | $3,366 | n/a |
UU0052 # 03 Y:2003 | 03 | 2003 | RECOVER WASTE HEAT FROM EQUIPMENT | $3,186 | $2,810 | n/a |
UU0052 # 05 Y:2003 | 05 | 2003 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $3,027 | $6,000 | n/a |
UU0052 # 06 Y:2003 | 06 | 2003 | INSTALL SPECTRAL REFLECTORS / DELAMP | $2,237 | $410 | n/a |
UU0052 # 04 Y:2003 | 04 | 2003 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,302 | $1,661 | n/a |
UU0052 # 01 Y:2003 | 01 | 2003 | OPTIMIZE PLANT POWER FACTOR | $12,731 | $22,600 | n/a |
UU0052 # 02 Y:2003 | 02 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,035 | $134 | n/a |
WI0450 # 04 Y:2003 | 04 | 2003 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $9,686 | $5,767 | Not Implemented |
WI0450 # 07 Y:2003 | 07 | 2003 | REPLACE CLOTH RAGS WITH PAPER TOWELS | $1,800 | $0 | Not Implemented |
WI0450 # 02 Y:2003 | 02 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $64,456 | $144,540 | n/a |
WI0450 # 03 Y:2003 | 03 | 2003 | UPGRADE CONTROLS ON COMPRESSORS | $10,369 | $22,000 | Not Implemented |
WI0450 # 01 Y:2003 | 01 | 2003 | REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER | $137,202 | $84,000 | Not Implemented |
WI0450 # 05 Y:2003 | 05 | 2003 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $5,580 | $12,500 | Not Implemented |
WI0450 # 06 Y:2003 | 06 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,604 | $7,821 | Not Implemented |
AS0356 # 05 Y:2003 | 05 | 2003 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $935 | $20 | Implemented |
AS0356 # 06 Y:2003 | 06 | 2003 | INSTALL OCCUPANCY SENSORS | $697 | $675 | Not Implemented |
AS0356 # 12 Y:2003 | 12 | 2003 | CLEAR AND RENT EXISTING SPACE | $96,000 | $8,340 | Implemented |