Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
257
matching recommendationsNAICS | 325 | Chemical Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IC0322 # 06 Y:2025 | 06 | 2025 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $25,000 | $1,250 | n/a |
IC0322 # 11 Y:2025 | 11 | 2025 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $205 | $144 | n/a |
IC0322 # 07 Y:2025 | 07 | 2025 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,658 | $693 | n/a |
IC0322 # 04 Y:2025 | 04 | 2025 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $15,262 | $24,421 | n/a |
IC0322 # 10 Y:2025 | 10 | 2025 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,536 | $2,000 | n/a |
IC0322 # 05 Y:2025 | 05 | 2025 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,041 | $210 | n/a |
IC0322 # 08 Y:2025 | 08 | 2025 | INSTALL TIMERS AND/OR THERMOSTATS | $4,457 | $211 | n/a |
IC0322 # 09 Y:2025 | 09 | 2025 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,919 | $0 | n/a |
IC0322 # 01 Y:2025 | 01 | 2025 | REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | $102,930 | $45,500 | n/a |
IC0322 # 03 Y:2025 | 03 | 2025 | INCREASE AMOUNT OF CONDENSATE RETURNED | $36,404 | $43,673 | n/a |
IC0322 # 02 Y:2025 | 02 | 2025 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT INCOMING FLUIDS | $5,455 | $41,668 | n/a |
IC0313 # 07 Y:2024 | 07 | 2024 | RECOVER WASTE HEAT FROM EQUIPMENT | $10,223 | $100,000 | n/a |
IC0313 # 11 Y:2024 | 11 | 2024 | INSULATE BARE EQUIPMENT | $4,631 | $8,869 | n/a |
IC0313 # 10 Y:2024 | 10 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,979 | $2,430 | n/a |
IC0313 # 09 Y:2024 | 09 | 2024 | REPAIR AND ELIMINATE STEAM LEAKS | $19,590 | $704 | n/a |
IC0313 # 08 Y:2024 | 08 | 2024 | ADOPT IN-HOUSE MATERIAL GENERATION | $75,451 | $92,231 | n/a |
IC0313 # 06 Y:2024 | 06 | 2024 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $1,557 | $0 | n/a |
IC0313 # 05 Y:2024 | 05 | 2024 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT INCOMING FLUIDS | $6,524 | $27,807 | n/a |
IC0313 # 04 Y:2024 | 04 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,107 | $6,125 | n/a |
IC0313 # 02 Y:2024 | 02 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,562 | $0 | n/a |
IC0313 # 01 Y:2024 | 01 | 2024 | OPTIMIZE OPERATION OF MULTI-STAGE VACUUM STEAM JETS | $9,651 | $7,079 | n/a |
IC0313 # 03 Y:2024 | 03 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $24,211 | $220,985 | n/a |
IC0229 # 04 Y:2019 | 04 | 2019 | ELIMINATE COOLING OF PROCESS STREAMS WHICH SUBSEQUENTLY MUST BE HEATED AND VICE VERSA | $2,133 | $2,010 | Implemented |
IC0229 # 06 Y:2019 | 06 | 2019 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $25,286 | $15,316 | Implemented |
IC0229 # 01 Y:2019 | 01 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,396 | $4,200 | Implemented |