Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
5,567
matching recommendationsNAICS | 325 | Chemical Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MI0300 # 16 Y:2016 | 16 | 2016 | CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS | $849 | $29 | Implemented |
SD0535 # 01 Y:2016 | 01 | 2016 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $324,317 | $112,783 | Implemented |
SD0535 # 02 Y:2016 | 02 | 2016 | USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT | $110,770 | $402,000 | Not Implemented |
SD0535 # 03 Y:2016 | 03 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $25,449 | $42,926 | Implemented |
SD0535 # 04 Y:2016 | 04 | 2016 | OPTIMIZE PLANT POWER FACTOR | $9,321 | $3,181 | Not Implemented |
SD0535 # 05 Y:2016 | 05 | 2016 | INSTALL OCCUPANCY SENSORS | $7,184 | $6,400 | Implemented |
SD0535 # 06 Y:2016 | 06 | 2016 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,708 | $200 | Not Implemented |
SD0535 # 07 Y:2016 | 07 | 2016 | USE WASTE HEAT STEAM FOR ABSORPTION REFRIGERATION | $710 | $3,100 | Not Implemented |
SD0533 # 01 Y:2016 | 01 | 2016 | USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT | $65,643 | $292,000 | Not Implemented |
SD0533 # 02 Y:2016 | 02 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $17,187 | $25,315 | Implemented |
SD0533 # 03 Y:2016 | 03 | 2016 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $11,672 | $7,800 | Implemented |
SD0533 # 04 Y:2016 | 04 | 2016 | OPTIMIZE PLANT POWER FACTOR | $4,856 | $2,339 | Not Implemented |
SD0533 # 05 Y:2016 | 05 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,056 | $1,000 | Implemented |
SD0533 # 06 Y:2016 | 06 | 2016 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $2,827 | $5,600 | Not Implemented |
SD0533 # 07 Y:2016 | 07 | 2016 | USE PHOTOCELL CONTROLS | $2,169 | $3,700 | Implemented |
AM0711 # 01 Y:2016 | 01 | 2016 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $62,500 | $108,300 | Not Implemented |
AM0711 # 02 Y:2016 | 02 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $25,350 | $57,195 | Implemented |
AM0711 # 03 Y:2016 | 03 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $22,630 | $9,030 | Implemented |
AM0711 # 04 Y:2016 | 04 | 2016 | OPTIMIZE PLANT POWER FACTOR | $18,515 | $60,200 | Not Implemented |
AM0711 # 05 Y:2016 | 05 | 2016 | REPAIR AND ELIMINATE STEAM LEAKS | $17,450 | $26 | Not Implemented |
AM0711 # 06 Y:2016 | 06 | 2016 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $11,000 | $13 | Not Implemented |
AM0711 # 07 Y:2016 | 07 | 2016 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $4,344 | $2,620 | Not Implemented |
AM0711 # 08 Y:2016 | 08 | 2016 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $2,880 | $0 | Implemented |
AM0711 # 09 Y:2016 | 09 | 2016 | USE SYNTHETIC LUBRICANT | $1,072 | $0 | Not Implemented |
AM0711 # 10 Y:2016 | 10 | 2016 | PAY BILLS ON TIME TO AVOID LATE FEES | $471 | $0 | Not Implemented |