Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
5,567
matching recommendationsNAICS | 325 | Chemical Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LE0414 # 05 Y:2016 | 05 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,482 | $10,500 | Implemented |
LE0414 # 06 Y:2016 | 06 | 2016 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $330 | $1,140 | Implemented |
WV0521 # 01 Y:2016 | 01 | 2016 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $26,401 | $25,760 | Not Implemented |
WV0521 # 02 Y:2016 | 02 | 2016 | UPGRADE CONTROLS ON COMPRESSORS | $10,186 | $8,000 | Implemented |
WV0521 # 03 Y:2016 | 03 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,543 | $2,714 | Not Implemented |
WV0521 # 04 Y:2016 | 04 | 2016 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,142 | $152 | Implemented |
WV0521 # 05 Y:2016 | 05 | 2016 | DEVELOP A REPAIR/REPLACE POLICY | $2,423 | $1,224 | Not Implemented |
WV0521 # 06 Y:2016 | 06 | 2016 | INSULATE BARE EQUIPMENT | $1,612 | $3,592 | Not Implemented |
WV0521 # 07 Y:2016 | 07 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $728 | $443 | Implemented |
WV0521 # 08 Y:2016 | 08 | 2016 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $718 | $500 | Implemented |
WV0521 # 09 Y:2016 | 09 | 2016 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $408 | $728 | Not Implemented |
DL0159 # 01 Y:2016 | 01 | 2016 | REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER | $287,810 | $31,000 | Implemented |
DL0159 # 02 Y:2016 | 02 | 2016 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $48,000 | $100,750 | Implemented |
DL0159 # 03 Y:2016 | 03 | 2016 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $7,300 | $17,825 | Implemented |
DL0159 # 04 Y:2016 | 04 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $28,590 | $188,100 | Implemented |
LE0409 # 01 Y:2016 | 01 | 2016 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $591 | $0 | Implemented |
LE0409 # 02 Y:2016 | 02 | 2016 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $2,416 | $2,000 | Implemented |
LE0409 # 03 Y:2016 | 03 | 2016 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $6,598 | $5,700 | Implemented |
LE0409 # 04 Y:2016 | 04 | 2016 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $13,605 | $43,760 | Not Implemented |
LE0409 # 05 Y:2016 | 05 | 2016 | USE RADIANT HEATER FOR SPOT HEATING | $6,148 | $21,000 | Implemented |
LE0409 # 06 Y:2016 | 06 | 2016 | USE SOLAR HEAT TO MAKE ELECTRICTY | $45,635 | $252,000 | Not Implemented |
NC0559 # 01 Y:2016 | 01 | 2016 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $109,787 | $1,000 | Implemented |
NC0559 # 02 Y:2016 | 02 | 2016 | REPLACE ELECTRIC MOTORS WITH BACK PRESSURE STEAM TURBINES AND USE EXHAUST STEAM FOR PROCESS HEAT | $28,202 | $75,000 | Not Implemented |
NC0559 # 03 Y:2016 | 03 | 2016 | REPLACE HIGH RESISTANCE DUCTS, PIPES, AND FITTINGS | $4,003 | $1,000 | Implemented |
NC0559 # 04 Y:2016 | 04 | 2016 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $5,720 | $10,000 | Not Implemented |