Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
524
matching recommendationsNAICS | 325 | Chemical Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MI0328 # 11 Y:2018 | 11 | 2018 | INSULATE BARE EQUIPMENT | $1,011 | $206 | Not Implemented |
UF0512 # 01 Y:2017 | 01 | 2017 | USE COMBINED CYCLE GAS TURBINE GENERATOR SETS WITH WASTE HEAT BOILERS CONNECTED TO TURBINE EXHAUST | $401,159 | $2,500,000 | Not Implemented |
UF0512 # 02 Y:2017 | 02 | 2017 | ISOLATE HOT OR COLD EQUIPMENT | $124,880 | $17,000 | Implemented |
UF0512 # 03 Y:2017 | 03 | 2017 | OPTIMIZE PLANT POWER FACTOR | $38,189 | $13,000 | Implemented |
UF0512 # 04 Y:2017 | 04 | 2017 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $23,030 | $40,000 | Not Implemented |
UF0512 # 05 Y:2017 | 05 | 2017 | USE CORRECT SIZE STEAM TRAPS | $27,893 | $340 | Implemented |
UF0512 # 06 Y:2017 | 06 | 2017 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $10,845 | $2,750 | Implemented |
UF0512 # 07 Y:2017 | 07 | 2017 | MINIMIZE CONDENSER COOLING WATER TEMPERATURE | $26,348 | $725 | Implemented |
UF0512 # 08 Y:2017 | 08 | 2017 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $9,636 | $6,225 | Implemented |
UF0512 # 09 Y:2017 | 09 | 2017 | INCREASE AMOUNT OF CONDENSATE RETURNED | $4,891 | $0 | Implemented |
UF0512 # 10 Y:2017 | 10 | 2017 | INSTALL COMMON HEADER ON COMPRESSORS | $3,951 | $11,185 | Implemented |
UF0512 # 11 Y:2017 | 11 | 2017 | COOL COMPRESSOR AIR INTAKE WITH HEAT EXCHANGER | $2,136 | $1,562 | Not Implemented |
UF0512 # 12 Y:2017 | 12 | 2017 | UTILIZE OTHER METHODS TO REMOVE CONTAMINANTS | $280,764 | $300,000 | Implemented |
UF0505 # 01 Y:2017 | 01 | 2017 | USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT | $715,231 | $1,700,000 | Not Implemented |
UF0505 # 02 Y:2017 | 02 | 2017 | REPLACE BOILER | $152,736 | $200,000 | Implemented |
UF0505 # 03 Y:2017 | 03 | 2017 | INCREASE AMOUNT OF CONDENSATE RETURNED | $18,902 | $2,800 | Implemented |
UF0505 # 04 Y:2017 | 04 | 2017 | ESTABLISH A PREVENTATIVE MAINTENANCE PROGRAM | $13,763 | $120 | Implemented |
UF0505 # 05 Y:2017 | 05 | 2017 | INSTALL TURBULATORS | $12,705 | $7,500 | Not Implemented |
UF0505 # 06 Y:2017 | 06 | 2017 | REPAIR AND ELIMINATE STEAM LEAKS | $7,831 | $1,081 | Implemented |
UF0505 # 07 Y:2017 | 07 | 2017 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $7,374 | $4,000 | Not Implemented |
UF0505 # 08 Y:2017 | 08 | 2017 | REPAIR AND ELIMINATE STEAM LEAKS | $4,554 | $1,592 | Implemented |
UF0501 # 01 Y:2017 | 01 | 2017 | USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT | $1,393,980 | $3,306,000 | Not Implemented |
UF0501 # 02 Y:2017 | 02 | 2017 | OPTIMIZE PLANT POWER FACTOR | $154,176 | $60,284 | Implemented |
UF0501 # 03 Y:2017 | 03 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $77,438 | $2,184 | Implemented |
UF0501 # 04 Y:2017 | 04 | 2017 | REPAIR AND ELIMINATE STEAM LEAKS | $32,236 | $1,794 | Implemented |