Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
5,567
matching recommendationsNAICS | 325 | Chemical Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
CO0692 # 01 Y:2014 | 01 | 2014 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,780 | $10,910 | Not Implemented |
CO0692 # 02 Y:2014 | 02 | 2014 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $39,420 | $1,250 | Implemented |
CO0692 # 03 Y:2014 | 03 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,790 | $21,020 | Implemented |
CO0690 # 01 Y:2014 | 01 | 2014 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,730 | $1,460 | Implemented |
CO0690 # 02 Y:2014 | 02 | 2014 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,180 | $0 | Implemented |
CO0690 # 03 Y:2014 | 03 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $940 | $370 | Implemented |
CO0690 # 04 Y:2014 | 04 | 2014 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $5,790 | $28,490 | Not Implemented |
CO0690 # 05 Y:2014 | 05 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,080 | $5,800 | Not Implemented |
WV0493 # 01 Y:2014 | 01 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $40,956 | $44,486 | Implemented |
WV0493 # 02 Y:2014 | 02 | 2014 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $19,168 | $5,300 | Implemented |
WV0493 # 03 Y:2014 | 03 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,848 | $509 | Implemented |
WV0493 # 04 Y:2014 | 04 | 2014 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $5,786 | $1,000 | Implemented |
WV0493 # 05 Y:2014 | 05 | 2014 | UPGRADE CONTROLS ON COMPRESSORS | $5,218 | $10,000 | Implemented |
WV0493 # 06 Y:2014 | 06 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,192 | $7,244 | Implemented |
WV0493 # 07 Y:2014 | 07 | 2014 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $5,090 | $0 | Not Implemented |
WV0493 # 08 Y:2014 | 08 | 2014 | INSULATE BARE EQUIPMENT | $3,507 | $1,251 | Implemented |
WV0493 # 09 Y:2014 | 09 | 2014 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,643 | $15 | Implemented |
WV0493 # 10 Y:2014 | 10 | 2014 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $2,071 | $1,000 | Not Implemented |
WV0493 # 11 Y:2014 | 11 | 2014 | DEVELOP A REPAIR/REPLACE POLICY | $1,391 | $661 | Not Implemented |
MZ0149 # 01 Y:2014 | 01 | 2014 | INSTALL OCCUPANCY SENSORS | $18,116 | $16,400 | Implemented |
MZ0149 # 02 Y:2014 | 02 | 2014 | INSTALL OCCUPANCY SENSORS | $4,128 | $6,040 | Implemented |
MZ0149 # 03 Y:2014 | 03 | 2014 | LOWER CEILING TO REDUCE CONDITIONED SPACE | $9,091 | $25,000 | Not Implemented |
MZ0149 # 04 Y:2014 | 04 | 2014 | LOWER CEILING TO REDUCE CONDITIONED SPACE | $6,580 | $25,750 | Not Implemented |
MZ0149 # 05 Y:2014 | 05 | 2014 | INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE) | $14,550 | $28,000 | Not Implemented |
MZ0149 # 06 Y:2014 | 06 | 2014 | AIR CONDITION ONLY SPACE NECESSARY | $46,961 | $5,500 | Not Implemented |