IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

249

matching recommendations
Reset
NAICS 325 Chemical Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
DL0171 # 06 Y:2016 06 2016 RECOVER WASTE HEAT FROM EQUIPMENT $2,076 $431 Not Implemented
DL0171 # 12 Y:2016 12 2016 TURN OFF EQUIPMENT WHEN NOT IN USE $4,030 $0 Implemented
DL0171 # 13 Y:2016 13 2016 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $890 $4,170 Not Implemented
DL0171 # 01 Y:2016 01 2016 INSTALL SYSTEM TO COLLECT SCRAP $4,328 $360 Not Implemented
DL0171 # 03 Y:2016 03 2016 LOWER COMPRESSOR PRESSURE THROUGH A/C SYSTEM MODIFICATION $374 $0 Implemented
DL0171 # 02 Y:2016 02 2016 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $4,059 $4,224 Not Implemented
DL0171 # 08 Y:2016 08 2016 RECOVER WASTE HEAT FROM EQUIPMENT $6,911 $588 Not Implemented
DL0171 # 04 Y:2016 04 2016 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $2,863 $11,400 Not Implemented
DL0171 # 10 Y:2016 10 2016 USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE $2,505 $1,524 Not Implemented
DL0171 # 11 Y:2016 11 2016 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $5,192 $3,840 Not Implemented
DL0171 # 05 Y:2016 05 2016 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $2,572 $11,400 Not Implemented
DL0171 # 07 Y:2016 07 2016 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS $2,885 $0 Implemented
DL0171 # 09 Y:2016 09 2016 INSTALL AUTOMATIC STACK DAMPER $624 $205 Not Implemented
DL0170 # 01 Y:2016 01 2016 UPGRADE CONTROLS ON COMPRESSORS $12,960 $23,000 Not Implemented
DL0170 # 02 Y:2016 02 2016 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $15,055 $40,740 Not Implemented
DL0170 # 03 Y:2016 03 2016 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,950 $9,830 Not Implemented
DL0170 # 04 Y:2016 04 2016 USE SOLAR HEAT TO MAKE ELECTRICTY $8,780 $47,412 Not Implemented
AM0718 # 04 Y:2016 04 2016 USE SYNTHETIC LUBRICANT $28,832 $0 Implemented
AM0718 # 05 Y:2016 05 2016 INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS $10,555 $1,800 Not Implemented
AM0718 # 01 Y:2016 01 2016 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $123,800 $195,000 Not Implemented
AM0718 # 02 Y:2016 02 2016 OPTIMIZE PLANT POWER FACTOR $53,431 $280,072 Not Implemented
AM0718 # 03 Y:2016 03 2016 USE STEAM PRESSURE REDUCTION TO GENERATE POWER $65,900 $400,000 Not Implemented
MA0762 # 01 Y:2016 01 2016 RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR $94,561 $209,164 Not Implemented
MA0762 # 03 Y:2016 03 2016 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $52,257 $19,975 Implemented
MA0762 # 02 Y:2016 02 2016 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $65,741 $161,899 Implemented