Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,015
matching recommendationsNAICS | 3251 | Basic Chemical Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NC0618 # 03 Y:2018 | 03 | 2018 | AVOID REWINDING MOTORS MORE THAN TWICE | $2,752 | $5,685 | Not Implemented |
NC0618 # 04 Y:2018 | 04 | 2018 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $12,341 | $2,450 | Not Implemented |
NC0618 # 05 Y:2018 | 05 | 2018 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $10,360 | $0 | Not Implemented |
NC0618 # 06 Y:2018 | 06 | 2018 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $3,172 | $500 | Not Implemented |
CL1806 # 01 Y:2018 | 01 | 2018 | REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | $66,598 | $22,500 | Not Implemented |
CL1806 # 02 Y:2018 | 02 | 2018 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $45,354 | $46,500 | Not Implemented |
CL1806 # 03 Y:2018 | 03 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $34,631 | $52,880 | Implemented |
CL1806 # 04 Y:2018 | 04 | 2018 | USE FLOW CONTROL VALVES ON EQUIPMENT TO OPTIMIZE WATER USE | $23,451 | $12,200 | Not Implemented |
CL1806 # 05 Y:2018 | 05 | 2018 | REPLACE TREATED WATER WITH WELL / SURFACE WATER | $7,271 | $4,700 | Not Implemented |
CL1806 # 06 Y:2018 | 06 | 2018 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $6,909 | $0 | Implemented |
UF0512 # 01 Y:2017 | 01 | 2017 | USE COMBINED CYCLE GAS TURBINE GENERATOR SETS WITH WASTE HEAT BOILERS CONNECTED TO TURBINE EXHAUST | $401,159 | $2,500,000 | Not Implemented |
UF0512 # 02 Y:2017 | 02 | 2017 | ISOLATE HOT OR COLD EQUIPMENT | $124,880 | $17,000 | Implemented |
UF0512 # 03 Y:2017 | 03 | 2017 | OPTIMIZE PLANT POWER FACTOR | $38,189 | $13,000 | Implemented |
UF0512 # 04 Y:2017 | 04 | 2017 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $23,030 | $40,000 | Not Implemented |
UF0512 # 05 Y:2017 | 05 | 2017 | USE CORRECT SIZE STEAM TRAPS | $27,893 | $340 | Implemented |
UF0512 # 06 Y:2017 | 06 | 2017 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $10,845 | $2,750 | Implemented |
UF0512 # 07 Y:2017 | 07 | 2017 | MINIMIZE CONDENSER COOLING WATER TEMPERATURE | $26,348 | $725 | Implemented |
UF0512 # 08 Y:2017 | 08 | 2017 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $9,636 | $6,225 | Implemented |
UF0512 # 09 Y:2017 | 09 | 2017 | INCREASE AMOUNT OF CONDENSATE RETURNED | $4,891 | $0 | Implemented |
UF0512 # 10 Y:2017 | 10 | 2017 | INSTALL COMMON HEADER ON COMPRESSORS | $3,951 | $11,185 | Implemented |
UF0512 # 11 Y:2017 | 11 | 2017 | COOL COMPRESSOR AIR INTAKE WITH HEAT EXCHANGER | $2,136 | $1,562 | Not Implemented |
UF0512 # 12 Y:2017 | 12 | 2017 | UTILIZE OTHER METHODS TO REMOVE CONTAMINANTS | $280,764 | $300,000 | Implemented |
SU0449 # 01 Y:2017 | 01 | 2017 | INSTALL / REPAIR INSULATION ON STEAM LINES | $2,375 | $267 | Not Implemented |
SU0449 # 02 Y:2017 | 02 | 2017 | ELIMINATE/REDUCE AN OPERATION | $1,271 | $900 | Not Implemented |
SU0449 # 03 Y:2017 | 03 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $194 | $208 | Not Implemented |