Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
413
matching recommendationsNAICS | 32519 | Other Basic Organic Chemical Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NL0056 # 05 Y:2021 | 05 | 2021 | INSTALL OCCUPANCY SENSORS | $1,169 | $770 | Implemented |
IP0121 # 07 Y:2019 | 07 | 2019 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $3,037 | $11,000 | Not Implemented |
IP0121 # 09 Y:2019 | 09 | 2019 | REPLACE BOILER | $11,538 | $50,526 | Not Implemented |
IP0121 # 05 Y:2019 | 05 | 2019 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $252 | $476 | Implemented |
IP0121 # 06 Y:2019 | 06 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,800 | $4,725 | Implemented |
IP0121 # 04 Y:2019 | 04 | 2019 | OPTIMIZE PLANT POWER FACTOR | $2,859 | $3,200 | Not Implemented |
IP0121 # 10 Y:2019 | 10 | 2019 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $3,795 | $17,400 | Implemented |
IP0121 # 08 Y:2019 | 08 | 2019 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $2,512 | $9,313 | Not Implemented |
IP0121 # 03 Y:2019 | 03 | 2019 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $1,721 | $260 | Implemented |
IP0121 # 02 Y:2019 | 02 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $662 | $23 | Implemented |
IP0121 # 01 Y:2019 | 01 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,409 | $5 | Not Implemented |
NL0031 # 01 Y:2019 | 01 | 2019 | USE OPTIMUM TEMPERATURE | $1,023,132 | $178,000 | Implemented |
NL0031 # 05 Y:2019 | 05 | 2019 | REPAIR AND ELIMINATE STEAM LEAKS | $5,225 | $1,600 | Not Implemented |
NL0031 # 04 Y:2019 | 04 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $12,390 | $24,394 | Implemented |
NL0031 # 03 Y:2019 | 03 | 2019 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $13,344 | $46,600 | Implemented |
NL0031 # 02 Y:2019 | 02 | 2019 | INSTALL TURBULATORS | $66,132 | $93,000 | Implemented |
NC0618 # 02 Y:2018 | 02 | 2018 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $909 | $750 | Not Implemented |
NC0618 # 03 Y:2018 | 03 | 2018 | AVOID REWINDING MOTORS MORE THAN TWICE | $2,752 | $5,685 | Not Implemented |
NC0618 # 01 Y:2018 | 01 | 2018 | CLEAN CONDENSER TUBES | $226,480 | $50,000 | Not Implemented |
NC0618 # 05 Y:2018 | 05 | 2018 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $10,360 | $0 | Not Implemented |
NC0618 # 06 Y:2018 | 06 | 2018 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $3,172 | $500 | Not Implemented |
NC0618 # 04 Y:2018 | 04 | 2018 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $12,341 | $2,450 | Not Implemented |
UF0512 # 03 Y:2017 | 03 | 2017 | OPTIMIZE PLANT POWER FACTOR | $38,189 | $13,000 | Implemented |
UF0512 # 01 Y:2017 | 01 | 2017 | USE COMBINED CYCLE GAS TURBINE GENERATOR SETS WITH WASTE HEAT BOILERS CONNECTED TO TURBINE EXHAUST | $401,159 | $2,500,000 | Not Implemented |
UF0512 # 02 Y:2017 | 02 | 2017 | ISOLATE HOT OR COLD EQUIPMENT | $124,880 | $17,000 | Implemented |