Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
945
matching recommendationsNAICS | 325211 | Plastics Material and Resin Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IC0089 # 07 Y:2004 | 07 | 2004 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $3,176 | $1,000 | Not Implemented |
IC0089 # 08 Y:2004 | 08 | 2004 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $26,684 | $90,950 | Not Implemented |
IC0089 # 09 Y:2004 | 09 | 2004 | UPGRADE OBSOLETE EQUIPMENT | $509 | $1,484 | Not Implemented |
AM0475 # 01 Y:2004 | 01 | 2004 | REPAIR OR REPLACE STEAM TRAPS | $19,000 | $650 | Implemented |
AM0475 # 02 Y:2004 | 02 | 2004 | REPAIR AND ELIMINATE STEAM LEAKS | $5,800 | $700 | Implemented |
AM0475 # 03 Y:2004 | 03 | 2004 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $5,390 | $500 | Implemented |
AM0475 # 04 Y:2004 | 04 | 2004 | USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER | $5,170 | $4,600 | Not Implemented |
AM0475 # 05 Y:2004 | 05 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,100 | $300 | Implemented |
AM0475 # 06 Y:2004 | 06 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,020 | $33 | Implemented |
AM0475 # 07 Y:2004 | 07 | 2004 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $4,290 | $400 | Not Implemented |
AM0475 # 08 Y:2004 | 08 | 2004 | INSTALL / REPAIR INSULATION ON STEAM LINES | $3,490 | $900 | Implemented |
AM0475 # 09 Y:2004 | 09 | 2004 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $1,600 | $12,500 | Not Implemented |
AM0475 # 10 Y:2004 | 10 | 2004 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $1,740 | $425 | Implemented |
AM0475 # 11 Y:2004 | 11 | 2004 | USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL | $572 | $699 | Not Implemented |
AM0475 # 12 Y:2004 | 12 | 2004 | INSULATE BARE EQUIPMENT | $450 | $60 | Not Implemented |
UF0350 # 01 Y:2004 | 01 | 2004 | DE-ENERGIZE EXCESS TRANSFORMER CAPACITY | $22,657 | $60,000 | Not Implemented |
UF0350 # 02 Y:2004 | 02 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,654 | $10,151 | Implemented |
UF0350 # 03 Y:2004 | 03 | 2004 | INSTALL OCCUPANCY SENSORS | $17,652 | $1,339 | Not Implemented |
UF0350 # 04 Y:2004 | 04 | 2004 | INSTALL SKYLIGHTS | $12,961 | $9,706 | Implemented |
UF0350 # 05 Y:2004 | 05 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,068 | $1,610 | Implemented |
UF0350 # 06 Y:2004 | 06 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $563 | $1,750 | Not Implemented |
UF0350 # 07 Y:2004 | 07 | 2004 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $8,988 | $0 | Not Implemented |
UF0350 # 08 Y:2004 | 08 | 2004 | RECYCLE FLUORESCENT LAMPS | $1,968 | $3,496 | Not Implemented |
UF0350 # 09 Y:2004 | 09 | 2004 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $4,200 | $0 | Not Implemented |
UF0350 # 10 Y:2004 | 10 | 2004 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $1,795 | $3,000 | Implemented |