IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

22

matching recommendations
Reset
NAICS 32561 Soap and Cleaning Compound Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
TR0025 # 06 Y:2020 06 2020 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $6,497 $9,060 Implemented
TR0025 # 05 Y:2020 05 2020 INSTALL OCCUPANCY SENSORS $371 $676 Implemented
TR0025 # 04 Y:2020 04 2020 REPAIR AND ELIMINATE STEAM LEAKS $1,683 $130 Implemented
TR0025 # 03 Y:2020 03 2020 USE OPTIMUM THICKNESS INSULATION $1,067 $830 Implemented
TR0025 # 02 Y:2020 02 2020 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,326 $1,145 Implemented
TR0025 # 01 Y:2020 01 2020 INSULATE BARE EQUIPMENT $657 $440 Implemented
AM0678 # 05 Y:2015 05 2015 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $365 $200 Implemented
AM0678 # 04 Y:2015 04 2015 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $520 $30 Not Implemented
AM0678 # 03 Y:2015 03 2015 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED $1,300 $0 Implemented
AM0678 # 02 Y:2015 02 2015 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $2,100 $690 Implemented
AM0678 # 01 Y:2015 01 2015 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,360 $1,300 Implemented
AM0521 # 11 Y:2007 11 2007 INSULATE BARE EQUIPMENT $180 $150 Not Implemented
AM0521 # 10 Y:2007 10 2007 OPTIMIZE PLANT POWER FACTOR $900 $1,620 Not Implemented
AM0521 # 09 Y:2007 09 2007 INSULATE BARE EQUIPMENT $1,200 $45 Not Implemented
AM0521 # 08 Y:2007 08 2007 PAY UTILITY BILLS ON TIME $2,066 $0 Implemented
AM0521 # 07 Y:2007 07 2007 INSTALL SKYLIGHTS $3,000 $3,320 Not Implemented
AM0521 # 06 Y:2007 06 2007 UPGRADE OBSOLETE EQUIPMENT $3,130 $2,000 Not Implemented
AM0521 # 05 Y:2007 05 2007 USE SYNTHETIC LUBRICANT $580 $0 Not Implemented
AM0521 # 04 Y:2007 04 2007 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $1,340 $8,050 Implemented
AM0521 # 03 Y:2007 03 2007 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $11,670 $20,000 Implemented
AM0521 # 02 Y:2007 02 2007 REPLACE BOILER $65,200 $150,000 Not Implemented
AM0521 # 01 Y:2007 01 2007 REPAIR OR REPLACE STEAM TRAPS $183,000 $1,635 Implemented