Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
923
matching recommendationsNAICS | 3259 | Other Chemical Product and Preparation Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TT0033 # 02 Y:2009 | 02 | 2009 | REPAIR OR REPLACE STEAM TRAPS | $78,500 | $40,000 | Implemented |
TT0033 # 03 Y:2009 | 03 | 2009 | RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER | $45,100 | $15,000 | Not Implemented |
TT0033 # 04 Y:2009 | 04 | 2009 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $18,000 | $36,000 | Not Implemented |
TT0033 # 05 Y:2009 | 05 | 2009 | INCREASE AMOUNT OF CONDENSATE RETURNED | $7,848 | $8,000 | Not Implemented |
TT0033 # 06 Y:2009 | 06 | 2009 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,616 | $2,500 | Implemented |
TT0033 # 07 Y:2009 | 07 | 2009 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $8,200 | $0 | Implemented |
TT0033 # 08 Y:2009 | 08 | 2009 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $24,600 | $27,800 | Implemented |
WV0383 # 06 Y:2008 | 06 | 2008 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,268 | $260 | Implemented |
WV0383 # 01 Y:2008 | 01 | 2008 | REDUCE VENTILATION AIR | $13,257 | $5,000 | Not Implemented |
WV0383 # 02 Y:2008 | 02 | 2008 | UPGRADE CONTROLS ON COMPRESSORS | $5,179 | $7,500 | Not Implemented |
WV0383 # 03 Y:2008 | 03 | 2008 | REPLACE BOILER | $4,983 | $9,450 | Implemented |
WV0383 # 04 Y:2008 | 04 | 2008 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,055 | $50 | Not Implemented |
WV0383 # 05 Y:2008 | 05 | 2008 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $2,337 | $1,049 | Not Implemented |
WV0383 # 07 Y:2008 | 07 | 2008 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,141 | $200 | Not Implemented |
WV0383 # 08 Y:2008 | 08 | 2008 | INSTALL OCCUPANCY SENSORS | $1,008 | $375 | Implemented |
WV0383 # 09 Y:2008 | 09 | 2008 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $1,006 | $2,125 | Not Implemented |
WV0383 # 10 Y:2008 | 10 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $742 | $1,995 | Implemented |
WV0383 # 11 Y:2008 | 11 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $655 | $0 | Implemented |
WV0383 # 12 Y:2008 | 12 | 2008 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $380 | $800 | Implemented |
WV0382 # 07 Y:2008 | 07 | 2008 | RECOVER WASTE HEAT FROM EQUIPMENT | $5,784 | $224 | Not Implemented |
WV0382 # 15 Y:2008 | 15 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $766 | $3,539 | Implemented |
WV0382 # 14 Y:2008 | 14 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $902 | $0 | Implemented |
WV0382 # 13 Y:2008 | 13 | 2008 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,076 | $31 | Implemented |
WV0382 # 12 Y:2008 | 12 | 2008 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $1,884 | $3,093 | Not Implemented |
WV0382 # 11 Y:2008 | 11 | 2008 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,016 | $195 | Implemented |