Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
32
matching recommendationsNAICS | 325998 | All Other Miscellaneous Chemical Product and Preparation Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LS0005 # 02 Y:2017 | 02 | 2017 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $25,903 | $21,300 | Implemented |
LS0005 # 03 Y:2017 | 03 | 2017 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,795 | $4,000 | Implemented |
LS0005 # 04 Y:2017 | 04 | 2017 | TURN OFF EQUIPMENT WHEN NOT IN USE | $7,832 | $100 | Implemented |
LS0005 # 05 Y:2017 | 05 | 2017 | INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE) | $134,326 | $621,739 | Not Implemented |
LS0005 # 06 Y:2017 | 06 | 2017 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $7,044 | $34,056 | Not Implemented |
LS0005 # 07 Y:2017 | 07 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,997 | $3,280 | Implemented |
LS0005 # 08 Y:2017 | 08 | 2017 | INSTALL TIMERS AND/OR THERMOSTATS | $330 | $400 | Implemented |
LS0005 # 09 Y:2017 | 09 | 2017 | INSTALL OCCUPANCY SENSORS | $347 | $585 | Implemented |
LS0005 # 01 Y:2017 | 01 | 2017 | OPTIMIZE PLANT POWER FACTOR | $69,401 | $106,209 | Not Implemented |
UK1705 # 05 Y:2017 | 05 | 2017 | REPAIR AND ELIMINATE STEAM LEAKS | $8,869 | $125 | Not Implemented |
UK1705 # 15 Y:2017 | 15 | 2017 | USE ONLY CERTIFIED MOTOR REPAIR SHOPS | $1,601 | $2,117 | Not Implemented |
UK1705 # 06 Y:2017 | 06 | 2017 | USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING | $3,629 | $3,632 | Not Implemented |
UK1705 # 07 Y:2017 | 07 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $72,754 | $132,800 | Not Implemented |
UK1705 # 08 Y:2017 | 08 | 2017 | USE PHOTOCELL CONTROLS | $35,448 | $9,500 | Not Implemented |
UK1705 # 09 Y:2017 | 09 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,348 | $5,168 | Not Implemented |
UK1705 # 10 Y:2017 | 10 | 2017 | USE PHOTOCELL CONTROLS | $1,504 | $3,570 | Not Implemented |
UK1705 # 11 Y:2017 | 11 | 2017 | TURN OFF EQUIPMENT WHEN NOT IN USE | $63,938 | $0 | Not Implemented |
UK1705 # 12 Y:2017 | 12 | 2017 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $9,503 | $2,284 | Not Implemented |
UK1705 # 13 Y:2017 | 13 | 2017 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $690 | $870 | Not Implemented |
UK1705 # 14 Y:2017 | 14 | 2017 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $18,931 | $0 | Not Implemented |
UK1705 # 04 Y:2017 | 04 | 2017 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $7,496 | $35,000 | Not Implemented |
UK1705 # 03 Y:2017 | 03 | 2017 | REPAIR AND ELIMINATE STEAM LEAKS | $664,167 | $12,740 | Not Implemented |
UK1705 # 02 Y:2017 | 02 | 2017 | USE WASTE HEAT FROM HOT FLUE GASES TO GENERATE STEAM | $1,101,438 | $3,000,000 | Not Implemented |
UK1705 # 01 Y:2017 | 01 | 2017 | PAY UTILITY BILLS ON TIME | $33,114 | $0 | Not Implemented |
SD0548 # 08 Y:2017 | 08 | 2017 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,052 | $360 | Implemented |